Mumbai/Project record

MahaRERA · the public record

Sai exotica

Mumbai Suburban · SAI SAVALI BUILDER

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000006841

Delivery and registration

When is the project declared for completion?

Sai exotica is registered with MahaRERA as P52000006841 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000006841
Registered on16 Aug 2017
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Sai exotica record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 30 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sai Savali Builder is the promoter of record on 14 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

14projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Sai exotica in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
wing-A1G+4-
Wing -B1G+4-
Wing-C1G+4-
Wing-D1G+4-
Wing-E1G+4-
Wing-F1G+4-
Wing -G1G+4-
Wing-H1G+4-
WING A11G+0-

Legal and disputes

What disputes are disclosed?

3 complaints are on the MahaRERA record for Sai exotica, with orders passed in 1 of them.

3complaints

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000005660817/10/2018Suresh Khandewale and Baban Shewale vs SANJAY MAHENDRA GUPTAorder passed
CC1250059520/02/2025SUDHAKAR KACHARU SHINDE vs SAI SAVALI BUILDERpending / no order on file
CC1260013608/01/2026Nagesh Ram Mahindrakar vs SAI SAVALI BUILDERpending / no order on file

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
LokayuktT-112014Deemed

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 410101. Per the filed land record, the plot is bounded to the north by 295, to the south by 297, to the east by 290 and to the west by 297. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~44 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park44 km
Bandra Kurla Complex (BKC)46 km
Chhatrapati Shivaji Int'l Airport47 km
Andheri MIDC / SEEPZ48 km
Lower Parel / Worli business district51 km
Nariman Point / Fort52 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Neral

Arsh Apartment
possession by Sep 2026 · Mateen Rafique Patel
Naaz Plaza
possession by Sep 2026 · Prestige Reality
Labdhi Gardens Phase 6
possession by Dec 2026 · Labdhi Lifestyle Limited
Labdhi Gardens Phase 7
possession by Dec 2026 · Labdhi Lifestyle Limited
Labdhi Gardens Phase 8
possession by Dec 2026 · Labdhi Lifestyle Limited
RAJ Baug Phase - III
possession by Dec 2026 · Nehaldhara Realtors

Major developers building in Neral

Other RERA-registered projects in Raigarh

SAI Galaxy
declared completion Jun 2024 · Lakhman Govabhai Bhateshra
SAI Gandh
declared completion Jan 2021 · Sharad Vishwanath Katre
Sai Ganesh
declared completion Jun 2026 · AAI Infrastructures
SAI Ganesh
possession by Dec 2026 · SAI Ganesh Reality
SAI Gardens
declared completion Dec 2014 · Rekha Subhash Jagdale
SAI Gaurav
declared completion Mar 2026 · SAI Shakti Builder

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026