Mumbai/Project record

MahaRERA · the public record

Sai Proviso Sapphire

Kalamboli · Proviso Builders and Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000021378

Delivery and registration

When is the project declared for completion?

Sai Proviso Sapphire is registered with MahaRERA as P52000021378 and the promoter has declared completion for 30 Jun 2023.

30 Jun 2023

declared completion

39months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000021378
Registered on24 Jun 2019
Promoter-declared completion30 Jun 2023
Current statusCertificate Signed
Against todayabout 39 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Sai Proviso Sapphire record 17 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 17 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Proviso Builders is the promoter of record on 9 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

9projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Sai Proviso Sapphire in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+21.

BuildingWingsFloorsDeclared completion
SAI PROVISO SAPPHIRE1G+2131 Dec 2022

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Sai Proviso Sapphire, with orders passed in 0 of them.

1complaint

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1260205407/04/2026Amrik Singh Sunder Singh Sunder Singh Singh vs Proviso Builders and Developerspending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered29 Jun 2024The date of completion of project was erroneously mentioned as 31.12.2022 instead of 31.12.2023. We have taken consent of Allottees for correcting the mistake of completion date. S

Location, Land & Connectivity

Located at Kalamboli, Sector-17, Thane, Thane, 410210. Per the filed land record, the plot is bounded to the north by 30 meter wide road, to the south by Plot No 51, to the east by Plot No 50 and to the west by 11 meter wide road. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Proviso Builders And Developers is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Kharghar

Tharwani Palladian
possession by Sep 2026 · Tharwani Realtors
Balaji Park
possession by Oct 2026 · Mohansingh Tararam Choudhary
Krishna Aura
possession by Oct 2026 · Qualitas Lifespaces LLP
Ashwini Apartment
possession by Dec 2026 · Kuldeepsingh Amarsingh Bhalothia
Bhagwati Luxuria
possession by Dec 2026 · Bhagwati Signature LLP
Elysian
possession by Dec 2026 · Devam Ventures

Major developers building in Kharghar

Other RERA-registered projects in Raigarh

Sai Regency
declared completion Dec 2022 · Aadhirath Construction
Sai Residency
possession by Dec 2027 · Saiyogi Developers LLP
SAI Residency
declared completion Feb 2021 · Shree Bramha Enterprises
SAI Sagar Residency
possession by Dec 2030 · Not Available
SAI Samarth
declared completion Dec 2021 · Arun Narayan Dhumal
SAI Sanskruti
declared completion Jun 2024 · Shree Sai Builders And Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026