05 Oct 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

05 Oct 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700019120

Delivery and registration

When is the project declared for completion?

SAI VRINDAVAN is registered with MahaRERA as P51700019120 and the promoter has declared completion for 05 Oct 2023.

05 Oct 2023

declared completion

35months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700019120
Registered on04 Jan 2019
Promoter-declared completion05 Oct 2023
Current statusCertificate Signed
Against todayabout 35 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAI VRINDAVAN record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAI VRINDAVAN in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+26.

BuildingWingsFloorsDeclared completion
SAI VRINDAVAN1G+2605 Oct 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at KOPERKHAIRNE, NAVI MUMBAI, PLOT NO 33, SECTOR 9, Panvel, Raigarh, 400706. Per the filed land record, the plot is bounded to the north by PLOT NO 34, to the south by PLOT NO 32, to the east by PLOT NO 36 and to the west by Proposed 24 mtrs wide Road. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

K T Realty is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by K T Realty

Other RERA-registered projects in Nerul

Cyber Code
possession by Sep 2026 · Greenscape Realty
Shreeji Dios
possession by Dec 2026 · Shreeji Ventures Nirmaan Private Limited
Infinity Ikon
possession by Dec 2026 · Emperia Projects
Plan I
possession by Dec 2026 · M/s. Tescon Plan-I LLP
Regency Palms Phase IV
possession by Dec 2026 · Regency INC
Sawan Serenity
possession by Dec 2026 · Shree Sawan Buildcon

Other RERA-registered projects in Thane

SAI Vrindavan
possession by Dec 2028 · M/S SAI Siddhi Enterprises
SAI Vyankatesh
declared completion Jun 2021 · Anjana Sahebrao Chavan
SAI World Dreams Commercial Building NO. 2
possession by Dec 2030 · Out N Out Infotech India LLP
SAI World Dreams Phase 1
possession by Dec 2028 · Out N Out Infotech India LLP
SAI World Dreams Phase 2
possession by Dec 2029 · Out N Out Infotech India LLP
SAI World Dreams Phase 3 Tower NO. 4 Spring
possession by Dec 2030 · Out N Out Infotech India LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026