Mumbai/Project record

MahaRERA · the public record

SAIRAJ

GHANSOLI · TUKARAM JADHAV AGASKAR

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

25 Mar 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

25 Mar 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700029720

Delivery and registration

When is the project declared for completion?

SAIRAJ is registered with MahaRERA as P51700029720 and the promoter has declared completion for 25 Mar 2023.

25 Mar 2023

declared completion

42months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700029720
Registered on26 Jun 2021
Promoter-declared completion25 Mar 2023
Current statusCertificate Signed
Against todayabout 42 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAIRAJ record 8 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 8 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Tukaram Jadhav Agaskar is the promoter of record on 69 projects registered with MahaRERA, 11 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

69projects

registered with MahaRERA

11flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAIRAJ in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
SAIRAJ1G+525 Mar 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at GHANSOLI, SEC - 21, Thane, Thane, 400701. Per the filed land record, the plot is bounded to the north by PLOT NO 151, to the south by PLOT NO 149, to the east by 11 MTR ROAD and to the west by -. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ghansoli

Alliaance Icon
possession by Dec 2026 · Satyam Infra
Gami Asters A Wing
possession by Dec 2026 · Thalia AND Gami Enterprises
Gami Asters B Wing
possession by Dec 2026 · Thalia AND Gami Enterprises
Kusum Residency
possession by Dec 2026 · Suresh Padman Patil
Goldcrest Residency - Phase 2
possession by Mar 2027 · Savita Homemakers LLP
Century TWO
possession by Mar 2028 · City Infra

Other RERA-registered projects in Thane

Sairaj Avenue Wing B
declared completion Jul 2026 · Virendra Atmaram Salunkhe
Sairaj Heights
possession by Mar 2027 · VPM Jairaj Developers
Sairatan Developers
declared completion Feb 2025 · Sairatan Developers
Saishyam Arcade
declared completion Dec 2025 · Shubh Buildspace
Sajan Shantaram Krupa
possession by Dec 2030 · Tirupati Developers
Saket Imperial
declared completion Aug 2025 · Nirmaan Realty

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026