MahaRERA Property Intelligence · Thane

SAIRAJ AVENUE

P51700048129 · BELAVALI · promoter Shri Sai Developers

Certificate SignedDue 20 Dec 2025

Delivery & Registration

MahaRERA registrationP51700048129
Registered on12 Dec 2022
Promoter-declared completion20 Dec 2025
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
SAIRAJ AVENUE WING-A1G+4-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
25 Dec 202324 Dec 2024Could not be able to complete the project and hence you are requested to accept the extension request.
25 Dec 202320 Dec 2025unavailability of materials and road re construction work and narrow road approching site

Location, Land & Connectivity

Located at BELAVALI, BADLAPUR AMBERNATH ROAD, Ambarnath, Thane, 421503. Per the filed land record, the plot is bounded to the north by PLOT NO 43, to the south by SHREE COMPLEX, to the east by PLOT NO 44 LAND and to the west by ORIENT LEGACY COMLPEX. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shri SAI Developers is the promoter on 11 MahaRERA-registered projects, of which 4 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Shri SAI Developers project & its RERA track record →

Other flagged projects by Shri SAI Developers

Shri SAI Developers
FlaggedRaigarh

Other RERA-registered projects in Badlapur

Ekdant Pooja Chsl
possession by Jul 2026 · Landmark Infra
OM Shiv Darshan
possession by Jul 2026 · Vinayak Enterprises Developers
RAJ Silverstone Phase-2
possession by Jul 2026 · Skyspace Builtek
Sairaj Avenue Wing B
possession by Jul 2026 · Virendra Atmaram Salunkhe
Satyam Sheela Wing F
possession by Jul 2026 · Shreeji Developers
Shreeji Greens
possession by Jul 2026 · Deep Laxmi Associates

Major developers building in Badlapur

Other RERA-registered projects in Thane

Sairaj Avenue Wing B
possession by Jul 2026 · Virendra Atmaram Salunkhe
Sairaj Emerald
declared completion Sep 2023 · Sairaj Enterprises
Sairaj Heights
possession by Mar 2027 · VPM Jairaj Developers
Sairam Parmeshwar CO. OP. Hsg. Soc. LTD
declared completion Jun 2025 · M/S Shiv Enterprises
Saish Enclave
declared completion Apr 2022 · Saish Infra
Saishiv Complex
declared completion Dec 2023 · Saishiv Construction

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026