Mumbai/Project record

MahaRERA · the public record

SAIRAJ RESIDENCY

ROHINJAN · SAIRAJ DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

16 Feb 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

16 Feb 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000024997

Delivery and registration

When is the project declared for completion?

SAIRAJ RESIDENCY is registered with MahaRERA as P52000024997 and the promoter has declared completion for 16 Feb 2023.

16 Feb 2023

declared completion

43months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000024997
Registered on18 Mar 2020
Promoter-declared completion16 Feb 2023
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAIRAJ RESIDENCY record 13 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 13 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sairaj Developers is the promoter of record on 48 projects registered with MahaRERA, 6 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

48projects

registered with MahaRERA

6flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAIRAJ RESIDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
SAIRAJ RESIDENCY1G+416 Feb 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at ROHINJAN, ROHINJAN PANVEL, Panvel, Raigarh, 410210. Per the filed land record, the plot is bounded to the north by PLOT NO 38 AND PLOT NO 47, to the south by 6 M WIDE ROAD ROHINJAN, to the east by PLOT NO 39 AND PLOT NO 40 and to the west by PLOT NO 44. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sairaj Developers is the promoter on 7 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Sairaj Developers

Other RERA-registered projects in Kharghar

Tharwani Palladian
possession by Sep 2026 · Tharwani Realtors
Balaji Park
possession by Oct 2026 · Mohansingh Tararam Choudhary
Krishna Aura
possession by Oct 2026 · Qualitas Lifespaces LLP
Ashwini Apartment
possession by Dec 2026 · Kuldeepsingh Amarsingh Bhalothia
Bhagwati Luxuria
possession by Dec 2026 · Bhagwati Signature LLP
Elysian
possession by Dec 2026 · Devam Ventures

Major developers building in Kharghar

Other RERA-registered projects in Raigarh

Saisha Apartment
declared completion Dec 2022 · Ramnath Motiram Karavkar
Sakaleshwar CHS Ltd
possession by Dec 2026 · S Plus Associates
Sakasi Park III
declared completion Dec 2023 · Jindal Builders And Developers
Sakha Heights
possession by Dec 2026 · Sakha Lifespace LLP
Sakha Jalaram
possession by Dec 2028 · Sakha Jalaram Homes LLP
Sakhu Residency
possession by Dec 2027 · Ankush Hadaku Madhavi

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026