Mumbai/Project record

MahaRERA · the public record

SAMRUDDHI RESIDENCY PHASE-1

Saphale West · Dharmi Constructions

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

54units filed as unsoldInventory · 16 September 2026
31 Dec 2027declared completionMahaRERA registration · read 12 Jul 2026
86registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000020901

Delivery and registration

When is the project declared for completion?

SAMRUDDHI RESIDENCY PHASE-1 is registered with MahaRERA as P99000020901 and the promoter has declared completion for 31 Dec 2027.

31 Dec 2027

declared completion

15months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000020901
Registered on16 May 2019
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today15 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAMRUDDHI RESIDENCY PHASE-1 record 35 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Dharmi Constructions is the promoter of record on 7 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

7projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In SAMRUDDHI RESIDENCY PHASE-1, ₹2.94 Cr of a declared ₹4.99 Cr estimated project cost is reported as incurred, about 59.0%, as at the last certified filing with MahaRERA.

59.0%

₹2.94 Cr

of ₹4.99 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In SAMRUDDHI RESIDENCY PHASE-1, 32 of 86 homes filed with MahaRERA are recorded as sold or booked, about 37%, and 54 remain available.

37%sold

32 of 86 homes

₹5.67 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹4.69 Cr (about 83%) is recorded as collected and ₹97.52 Lakh as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 32 registered agreements, the effective carpet rate is ₹4,476/sqft, with eight in ten falling between ₹3,798 and ₹5,772 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 16 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 32 homes carry one, and 54 of the 86 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
3324 sqftRs 4,331 a sq ft typical, over Rs 3,579 to Rs 5,7727 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In SAMRUDDHI RESIDENCY PHASE-1, 22 of the 54 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 53 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4 and 86 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Building No-31G+42931 May 2023
Building No-41G+43031 May 2023
Building No-51G+42731 May 2023

Unit mix on the filing: 86 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered29 May 2025due to labour and material issue
29 May 202531 Dec 2027Two of the three buildings are already almost completed but the third (B-5) building works are not yet started (not even a single unit is old in that building). Hence asking for e

Location, Land & Connectivity

Located at Saphale West, Virathan Khurd, Palghar, Palghar, 401102. Per the filed land record, the plot is bounded to the north by 15m Wide Road, to the south by S No 56-6, to the east by S No 56-2 Pt and to the west by S No 56-2 Pt. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~50 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ50 km
Powai / Hiranandani business park52 km
Chhatrapati Shivaji Int'l Airport55 km
Bandra Kurla Complex (BKC)57 km
Lower Parel / Worli business district65 km
Nariman Point / Fort73 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Makane

Excellence Residency 3
possession by Dec 2026 · SAI Excellence Developers
Nayan-Vastu Heritage
Not filing quarterly progress reports · possession by Dec 2026 · Unity Infra
Nayan-Vastu Heritage
possession by Dec 2026 · Unity Infra
Nine Star Prestige Building NO. 1
possession by Dec 2026 · Nine Home Creators
Nine Star Prestige Building NO. 2
possession by Dec 2026 · Nine Home Creators
Ninestar Crown Bldg NO 5 Emerald
possession by Dec 2026 · Nine Homemakers

Other RERA-registered projects in Palghar

Samya ONE
possession by Dec 2028 · Primeville Developers LLP
Saniya City
declared completion Jun 2025 · Zeeshan Yusuf Qureshi
Sanjari Phase 2
declared completion Mar 2026 · Amin Valibhai Chotaliya
Sankalp Heights Building No 2 D E F Wing Phase 1 Ground Plus 7th Floor And Phase 2 8th Plus 12 Floor
possession by Dec 2027 · Sankalp Builders And Developers
Sankalp Shrushthi Building NO 3 Wing I J AND K
declared completion Dec 2023 · Sankalp Buildcon
Sanmukh Sunshine
possession by Oct 2026 · Sanmukh Realty LLP

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026