MahaRERA Property Intelligence · Palghar

SATHYA LIFESTYLES PHASE 2

P99000006980 · promoter Sathya Lifestyles Pvt

Certificate SignedDue 30 Mar 2024

Delivery & Registration

MahaRERA registrationP99000006980
Registered on17 Aug 2017
Promoter-declared completion30 Mar 2024
Current statusCertificate Signed
Against todayabout 28 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sathya Lifestyles Pvt is the promoter of record on 49 projects, of which 4 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
BUILDING 111G+4-
BUILDING 131G+4-

Complaints & Orders

9 complaints are on the MahaRERA record for this project, with orders passed in 9. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000001211508/12/2017DEVENDRA PRATAP SINGH vs SATHYA LIFESTYLES PVT. LTD.order passed
CC00600000001246929/12/2017DEVENDRA PRATAP SINGH vs SATHYA LIFESTYLES PVT. LTD.order passed
CC00600000002326716/02/2018JOAQUIM C. FERNANDES vs SATHYA LIFESTYLES PVT. LTD.order passed
CC00600000005574410/08/2018ATUL MANGESH JADHAV vs SATHYA LIFESTYLES PVT. LTD.order passed
CC00600000000128617/10/2017Sharbari Nagfernandes vs Sathya Lifestyles Pvt Ltdorder passed
CC00600000005690914/11/2018DEVENDRA PRATAP SINGH vs SATHYA LIFESTYLES PVT. LTD.order passed
CC00600000039700611/08/2023Sudhakar Yeswant Mandrekar vs Sathya Lifestyles Pvt Ltdorder passed
CC1250061121/02/2025Ravi Krishnan Ganeshan vs SATHYA LIFESTYLES PVT LTDorder passed
CC1250061222/02/2025Prashant Nakhwa vs SATHYA LIFESTYLES PVT LTDorder passed

Legal & Litigation

The promoter has declared 4 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Consumer Court6442016Hearing Pending
Consumer Court8062016Hearing Pending
Consumer Court8082016Hearing Pending
Consumer Court8092016Hearing Pending

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 401404. Per the filed land record, the plot is bounded to the north by BY SNO 3 PART AND ROAD, to the south by PHASE 3, to the east by BY GAUTHAN AND ROAD and to the west by BY CANAL SERVICE ROAD AND KLG. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~65 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ65 km
Powai / Hiranandani business park66 km
Chhatrapati Shivaji Int'l Airport69 km
Bandra Kurla Complex (BKC)72 km
Lower Parel / Worli business district79 km
Nariman Point / Fort87 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Palghar

Shree SAI Apartment
possession by Jul 2026 · Shree SAI Jivdani Developers
Madhav Vatika - VI
possession by Jul 2026 · R M N H Developers LLP
Prithvi Anand Kuber Complex
possession by Jul 2026 · Prithvi Anand Housing And Land Developer
Vardhaman Divine
possession by Jul 2026 · Vardhaman AND Shah Associates
Symphony Heights
possession by Aug 2026 · Kreate Space LLP
Shree Puram - 2, Building No. 1
possession by Aug 2026 · Vastu Realities

Major developers building in Palghar

Other RERA-registered projects in Palghar

Sathyanagar Phase 1
declared completion Jan 2021 · Sapphire Space Infracon Pvt Ltd
Sathyanagar Phase 2
declared completion Jan 2021 · Sapphire Space Infracon Pvt Ltd
Sathyanagar Phase 3
declared completion Jan 2021 · Sapphire Space Infracon Pvt Ltd
Sathyanagar Phase 4
declared completion Jan 2021 · Sapphire Space Infracon Pvt Ltd
Sathyanagar Phase 5
declared completion Jan 2021 · Sapphire Space Infracon Pvt Ltd
Satu Aura
declared completion May 2018 · Satu Realty

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026