Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP51700011846
Registered on31 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Aakash Builders Developers is the promoter of record on 17 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
SEA GREEN APARTMENT1G+6-

Complaints & Orders

5 complaints are on the MahaRERA record for this project, with orders passed in 5. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000019293608/03/2020AMAR SINGH CHUAHAN vs AAKASH BUILDERS & DEVELOPERSorder passed
CC00600000019519321/12/2020DHARAMSEN RATILAL YADAV vs AAKASH BUILDERS & DEVELOPERSorder passed
CC00600000019535623/12/2020PRAMOD KUMAR SINGH vs AAKASH BUILDERS & DEVELOPERSorder passed
CC00600000019538817/01/2021Dr. Akhilesh D. Shukla & Mrs. Kanchan Akhilesh Shukla vs AAKASH BUILDERS & DEVELOPERSorder passed
CC00600000019796712/08/2021MR SURYAKANT BANSHIDHAR SHUKLA vs Aakash Builders & Developersorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202230 Dec 2022Due to Covid there were Issues regarding the Labour Supply as well as the Materials on Site, currently we have started our work in full swing and as per the consent of our booked c
30 Dec 202230 Jun 2021Due to Covid 19.

Location, Land & Connectivity

Located at Thane, Thane, 401107. Per the filed land record, the plot is bounded to the north by Open plot, to the south by DP ROAD, to the east by OPEN PLOT and to the west by OPEN PLOT. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~17 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ17 km
Powai / Hiranandani business park19 km
Chhatrapati Shivaji Int'l Airport22 km
Bandra Kurla Complex (BKC)24 km
Lower Parel / Worli business district32 km
Nariman Point / Fort40 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mira Road East

Ganesh Darshan
possession by Jul 2026 · J.v. Realty
Savaliya Residency
possession by Jul 2026 · Shree Savaliya Housing LLP
127 RAJ Homes A Wing
possession by Aug 2026 · RAJ Homes
Beaumonde
possession by Sep 2026 · Kanungo Property
Rassaz Greens Tower C D AND E
possession by Dec 2026 · Rassaz Infrastructure Private Limited
Coral
Deregistered by MahaRERA · possession by Dec 2026 · Nilesh Shantilal Tank

Major developers building in Mira Road East

Other RERA-registered projects in Thane

SEA Green Aurus
possession by Feb 2027 · Sea Green Homes
SEA Green Palacia
declared completion Jun 2026 · Seagreen Lifespaces LLP
SEA Green THE Royale
declared completion Jun 2019 · Satguru Developers
Sea Palace
declared completion Dec 2024 · Sanjeev Vasant Divekar
Seabreeze At Godrej Bayview
possession by Dec 2030 · Suncity Infrastructures LLP
Seagreen Rudra
possession by Dec 2029 · Seagreen Superstructures LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026