Mumbai/Project record

MahaRERA · the public record

SEVEN ELEVEN COMPLEX

MIRA ROAD EAST · MAHAVIR ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700010750

Delivery and registration

When is the project declared for completion?

SEVEN ELEVEN COMPLEX is registered with MahaRERA as P51700010750 and the promoter has declared completion for 30 Jun 2018.

30 Jun 2018

declared completion

99months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700010750
Registered on31 Aug 2017
Promoter-declared completion30 Jun 2018
Current statusCertificate Signed
Against todayabout 99 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SEVEN ELEVEN COMPLEX record 4 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 4 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Mahavir Enterprises is the promoter of record on 134 projects registered with MahaRERA, 10 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

134projects

registered with MahaRERA

10flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SEVEN ELEVEN COMPLEX in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+19.

BuildingWingsFloorsDeclared completion
SEVEN ELEVEN COMPLEX A1G+19-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at MIRA ROAD EAST, MIRA BHAYANDAR ROAD, Thane, Thane, 401107. Per the filed land record, the plot is bounded to the north by SURVEY NO 56, to the south by SURVEY NO 171 AND 30MT DP ROAD, to the east by SURVEY NO 62 AND 30 MT DP ROAD and to the west by SURVEY NO 178. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~19 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ19 km
Powai / Hiranandani business park20 km
Chhatrapati Shivaji Int'l Airport23 km
Bandra Kurla Complex (BKC)26 km
Lower Parel / Worli business district34 km
Nariman Point / Fort42 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Mahavir Enterprises is the promoter on 10 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Mahavir Enterprises project & its RERA track record →

Other flagged projects by Mahavir Enterprises

Mahavir Enterprises
FlaggedRaigarh

Other RERA-registered projects in Mira Road East

Beaumonde
possession by Sep 2026 · Kanungo Property
Rassaz Greens Tower C D AND E
possession by Dec 2026 · Rassaz Infrastructure Private Limited
Coral
Deregistered by MahaRERA · possession by Dec 2026 · Nilesh Shantilal Tank
JP North Aviva
possession by Dec 2026 · JP Infra Realty Private Limited
Prithvi Sneh
Deregistered by MahaRERA · possession by Dec 2026 · Prithvi Buildworth Constructions
Shree RAM Heights
possession by Dec 2026 · Vavya Enterprises

Major developers building in Mira Road East

Other RERA-registered projects in Thane

Seven Eleven Construction Apna Ghar
declared completion Sep 2018 · Narendra Lalchand Mehta
Seven Eleven Courtyard
possession by Mar 2029 · S.s.s Assoicates
Seven Heights
declared completion Dec 2025 · Ovais Mudabbir Bardi
Seven Square Avenue
possession by Dec 2028 · M/S Shubh Realty
Shabri Residency
declared completion Dec 2022 · Shree Ayyappa Constructions
Shagun Avasa
possession by Dec 2028 · Jalaram Enterprise

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026