SEVEN HEIGHTS

P99000047103 · BOISAR EAST · promoter Aditi Builders And

Certificate SignedDue 31 Dec 2025

Delivery & Registration

MahaRERA registrationP99000047103
Registered on03 Oct 2022
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Aditi Builders And is the promoter of record on 25 projects, of which 5 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
SEVEN HEIGHTS BULD NO 2, A WING1G+431 Dec 2025
SEVEN HEIGHTS BULD NO2, B WING1G+431 Dec 2025
SEVEN HEIGHTS, BULD NO 2, C WING1G+431 Dec 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at BOISAR EAST, TATA HOUSING ROAD, Vasai, Palghar, 401501. Per the filed land record, the plot is bounded to the north by JUPITER COMPLEX, to the south by BALAJI PROJECT, to the east by OPEN SPACE and to the west by RUKHMINI ENCLAVE. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~64 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ64 km
Powai / Hiranandani business park66 km
Chhatrapati Shivaji Int'l Airport68 km
Bandra Kurla Complex (BKC)71 km
Lower Parel / Worli business district78 km
Nariman Point / Fort86 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Aditi Builders AND Developers is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Aditi Builders AND Developers

Aditi Builders AND Developers
Not filing quarterly progress reportsThane

Other RERA-registered projects in Boisar

Ostwal Dream Land Phase - II
possession by Jul 2026 · Shree Ostwal Builders LTD
Parvati Homes
possession by Jul 2026 · Iconic Developers
Queens Villa
possession by Jul 2026 · Shashi Kuldeep Ostwal
Classic Apartment
possession by Sep 2026 · I.k.group
Divyajal
possession by Sep 2026 · Divyaraj Properties LLP
Kinjal Complex II
possession by Sep 2026 · Kinjal Enterprises

Major developers building in Boisar

Other RERA-registered projects in Palghar

Shadawal Impression Building C1 C2
declared completion Dec 2018 · Kailash Builders
Shagun Apartment
declared completion Nov 2024 · Shagun Developers
Shah Heights
possession by Dec 2026 · P.v.associates
Shaikh Residency
possession by Mar 2030 · M/s Shaikh Builders And Developers
Shail Pushp
declared completion Mar 2022 · Aditya Builders
Shakti Industrial Estate
possession by Dec 2026 · Shakti Krupa Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026