Mumbai/Project record

MahaRERA · the public record

SHAMIANA BY SGPH LLP

VILE PARLE (WEST) · SAI TATTVA ESTATES LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

6units filed as unsoldInventory · 19 September 2026
31 Mar 2027declared completionMahaRERA registration · read 12 Jul 2026
33registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800056183

Delivery and registration

When is the project declared for completion?

SHAMIANA BY SGPH LLP is registered with MahaRERA as P51800056183 and the promoter has declared completion for 31 Mar 2027.

31 Mar 2027

declared completion

6months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800056183
Registered on16 May 2024
Promoter-declared completion31 Mar 2027
Current statusCertificate Signed
Against today6 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHAMIANA BY SGPH LLP record 9 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Sai Tattva Estates is the promoter of record on 4 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

4projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In SHAMIANA BY SGPH LLP, ₹23.59 Cr of a declared ₹31.98 Cr estimated project cost is reported as incurred, about 73.8%, as at the last certified filing with MahaRERA.

73.8%

₹23.59 Cr

of ₹31.98 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In SHAMIANA BY SGPH LLP, 3 of 13 homes filed with MahaRERA are recorded as sold or booked, about 23%, and 10 remain available.

23%sold

3 of 13 homes

₹8.68 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹2.19 Cr (about 25%) is recorded as collected and ₹6.50 Cr as receivable. The project registers 33 homes in total, while this sold/unsold inventory filing covers 13 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 1104685 sqft (63.66 sqm)₹1.71 Cr
Floor 2202735 sqft (68.31 sqm)₹1.84 Cr
Floor 7701890 sqft (82.71 sqm)₹2.23 Cr
Floor 7702890 sqft (82.71 sqm)₹2.20 Cr
Floor 7703890 sqft (82.71 sqm)₹2.23 Cr
Floor 7704880 sqft (81.78 sqm)₹2.23 Cr
Floor 8802890 sqft (82.71 sqm)₹2.23 Cr
Floor 8803890 sqft (82.71 sqm)₹2.20 Cr
Floor 8804880 sqft (81.78 sqm)₹2.23 Cr
Floor 9902890 sqft (82.71 sqm)₹2.20 Cr

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 19 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 7 homes carry one, and 6 of the 13 are recorded unsold. Since we started watching this ledger, 4 homes have moved out of the unsold list, most recently on 11 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
702890 sqftRs 2.7820 cr typical, over Rs 2.6200 cr to Rs 2.8939 cr6 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In SHAMIANA BY SGPH LLP, 5 of the 6 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 5 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10 and 33 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
SHAMIANA BY SGPH LLP1G+1033-

Unit mix on the filing: 33 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at VILE PARLE (WEST), IRLA LANE, Mumbai, Mumbai Suburban, 400056. Per the filed land record, the plot is bounded to the north by ADJOINING PLOT CTS 744 1, to the south by 13 4 MT WIDE IRLA ROAD, to the east by ADJOINING PLOT CTS 744 5 and to the west by ADJOINING PLOT CTS 688 32. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vile Parle West

Tulsidham CHS
possession by Sep 2026 · SM & Happy Home Associates
56 Park Avenue
possession by Dec 2026 · Krishang Infra Private Limited
Ajmera Shringaar
possession by Dec 2026 · H J Corporation
Durga Gayatri
possession by Dec 2026 · Manoj Mohanlal Goradia
Eden 62
possession by Dec 2026 · Ekta Nagpal Ventures LLP
Meera Kunj
possession by Dec 2026 · Arham Realty

Other RERA-registered projects in Mumbai Suburban

Shamikh Building
declared completion Mar 2026 · Tamos Associates
Shan Windsor
possession by Dec 2026 · Shan Enterprise
Shangrila
possession by Dec 2026 · Pardis Tirumala LLP
Shankar Bhavan Premises Co-Operative Society Limited
declared completion Jun 2026 · Mishal Construction Private Limited
Shankar Darshan CHS LTD
possession by Dec 2026 · Majestic Royale Developers
Shankeshwar Apartment
possession by Dec 2026 · Navkar Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026