SHANTI ONE

SHANTINAGAR MIRAROAD · SHANTISTAR BUILDERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700003278

Delivery and registration

When is the project declared for completion?

SHANTI ONE is registered with MahaRERA as P51700003278 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700003278
Registered on05 Aug 2017
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHANTI ONE record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 30 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Shantistar Builders is the promoter of record on 4 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

4projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHANTI ONE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
22A AND 23A1G+1131 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2023Our Project is almost 100% complete except installation of Lift and some external work. Mean time our Architect has already applied to MCGM for issue of Occupation Certificate rec
30 Dec 202330 Dec 2024WE HEREBY APPLY FOR EXTENSION u/s 7(3) of the REGISTERED PROJECT BEARING REG. No. P51700003278 BECAUSE WE HAVE APPLIED BUT OCCUPANCY CERTIFICATE NOT RECD TILL FROM LOCAL AUTHORITY

Location, Land & Connectivity

Located at SHANTINAGAR MIRAROAD, 100 FEET ROAD, Mumbai City, Mumbai City, 401107. Per the filed land record, the plot is bounded to the north by BLDG NO B-22-23, to the south by OPEN PLOT R G, to the east by GARDEN and to the west by INTERNAL ROAD OF SECTOR 1. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~17 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ17 km
Powai / Hiranandani business park19 km
Chhatrapati Shivaji Int'l Airport22 km
Bandra Kurla Complex (BKC)24 km
Lower Parel / Worli business district32 km
Nariman Point / Fort40 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shantistar Builders is the promoter on 4 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Mira Road East

Beaumonde
possession by Sep 2026 · Kanungo Property
Rassaz Greens Tower C D AND E
possession by Dec 2026 · Rassaz Infrastructure Private Limited
Coral
Deregistered by MahaRERA · possession by Dec 2026 · Nilesh Shantilal Tank
JP North Aviva
possession by Dec 2026 · JP Infra Realty Private Limited
Prithvi Sneh
Deregistered by MahaRERA · possession by Dec 2026 · Prithvi Buildworth Constructions
Shree RAM Heights
possession by Dec 2026 · Vavya Enterprises

Major developers building in Mira Road East

Other RERA-registered projects in Thane

Shanti Park
declared completion Dec 2021 · V R Realties
Shantiniketan Wing B6
declared completion Dec 2021 · Anmol Associates
Shanu Majestic
possession by Dec 2026 · Fortune Group Of Construction
Shapoorji Pallonji Skyraa At Northern Lights
possession by Dec 2031 · Jaykali Developers Private Limited
Shapoorji Pallonji The Impulse
declared completion Dec 2023 · Jaykali Developers Private Limited
Shapoorji Pallonji The Impulse- Phase 1
possession by Jun 2028 · Jaykali Developers Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026