Mumbai/Project record

MahaRERA · the public record

SHIKHAR B

Jogeshwari West · Orbit Ventures Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2027declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800008213

Delivery and registration

When is the project declared for completion?

SHIKHAR B is registered with MahaRERA as P51800008213 and the promoter has declared completion for 30 Jun 2027.

30 Jun 2027

declared completion

9months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800008213
Registered on18 Aug 2017
Promoter-declared completion30 Jun 2027
Current statusCertificate Signed
Against today9 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHIKHAR B record 35 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 35 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Orbit Ventures Developers is the promoter of record on 15 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

15projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In SHIKHAR B, ₹9.91 Cr of a declared ₹450.41 Cr estimated project cost is reported as incurred, about 2.2%, as at the last certified filing with MahaRERA.

2.2%

₹9.91 Cr

of ₹450.41 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHIKHAR B in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+43.

BuildingWingsFloorsDeclared completion
SHIKHAR B1G+4331 Dec 2023

Legal and disputes

What disputes are disclosed?

11 complaints are on the MahaRERA record for SHIKHAR B, with orders passed in 9 of them.

11complaints

9with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000010031929/07/2019Suraj Kishore Khubchandani vs orbit ventures developersorder passed
CC00600000019466928/10/2020Naveenkumar Suryabhan Singh vs Orbit Ventures Developersorder passed
CC00600000019470928/10/2020Sanjaykumar Madhusudan yadav vs Orbit Ventures Developersorder passed
CC00600000019471028/10/2020Mr. Raju Sant Bahadur Chhetri vs Orbit Ventures Developersorder passed
CC00600000020999511/02/2022Sandeep Jadhwani and Araina Jadhwani vs Orbit Venture Developersorder passed
CC1250302227/08/2025Raju Sant bahadhur Chhetri vs Orbit Ventures Developersorder passed
CC1250309403/09/2025Sandeep Jadhwani vs Orbit Ventures Developerspending / no order on file
CC1250314306/09/2025Sanjaykumar Madhusudan Yadav vs Orbit Ventures Developersorder passed
CC1250367615/10/2025NAVEENKUMAR SURYABHAN SINGH vs Orbit Ventures Developersorder passed
CC1260178527/03/2026Anand Gupta vs Orbit Ventures Developersorder passed
CC1260434211/07/2026Anand B Gupta vs Orbit Ventures Developerspending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2027The Promoter respectfully submits that the delay in completion of the project was neither deliberate nor due to any negligence, but solely attributable to circumstances and events

Location, Land & Connectivity

Located at Jogeshwari West, Andheri Link Road, Andheri, Mumbai Suburban, 400102. Per the filed land record, the plot is bounded to the north by D P ROAD, to the south by PLOT NO R-5, to the east by SHIV SHIVAM BUILDINGS and to the west by PLOT NO R-7. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Chhatrapati Shivaji Int'l Airport7 km
Powai / Hiranandani business park8 km
Bandra Kurla Complex (BKC)9 km
Lower Parel / Worli business district16 km
Nariman Point / Fort24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Orbit Ventures Developers is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Jogeshwari West

Aksa Tower
possession by Sep 2026 · HFI Industries
GSA Grandeur
Past its declared completion date · possession by Oct 2026 · G S A Constructions
Lashkaria Pearl
possession by Nov 2026 · Lashkaria Housing & Infrastructure P
A H Avenue
possession by Dec 2026 · A.h. Constructions
KEY Tech Park
possession by Dec 2026 · M/s Keytech
Universal Garden- B Wing
possession by Dec 2026 · Pagarani Universal Infrastructure Pvt Lt

Major developers building in Jogeshwari West

Other RERA-registered projects in Mumbai Suburban

Shikhhar
possession by Sep 2026 · Mahavir Land Developer
Shilp Sangeet CO-OP Housing Society LTD
possession by Mar 2028 · S S Enterprises
Shilpa Grandeur
possession by Jun 2028 · SJK Buildcon LLP
Shilptaru Residency
declared completion Jun 2025 · Konark Shakti Group Of Company
Shiv Aaradhana
possession by Dec 2026 · Brightmen Buildspaces LLP
Shiv Aashray
possession by Jan 2028 · Shiva Rameehans Constructions LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026