Mumbai/Project record

MahaRERA · the public record

SHIV CASTLE

Mumbai Suburban · SUNIL SHANKAR BHOSLE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

20 Jun 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

20 Jun 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000003891

Delivery and registration

When is the project declared for completion?

SHIV CASTLE is registered with MahaRERA as P52000003891 and the promoter has declared completion for 20 Jun 2022.

20 Jun 2022

declared completion

51months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000003891
Registered on06 Aug 2017
Promoter-declared completion20 Jun 2022
Current statusCertificate Signed
Against todayabout 51 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHIV CASTLE record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHIV CASTLE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
SHIV CASTLE1G+7-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for SHIV CASTLE, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000039613919/07/2023Divesh Ramesh Kubal vs Sunil Shankar Bhosleorder passed
CC00600000039618731/10/2023Santosh Pitabas Panigrahi vs SUNIL SHANKAR BHOSLEorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered20 Dec 2021The project got delayed due to following reasons a) Slag in real estate market for residential properties b) Acute financial crunch and also, c) Covid 19 resulted in labour shor

Location, Land & Connectivity

Located at Mumbai, Mumbai Suburban, 410201. Per the filed land record, the plot is bounded to the north by 15 METER WIDE DP ROAD, to the south by HISSA NO 2, to the east by PLOT 2 and to the west by HISSA NO 5. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~51 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park51 km
Bandra Kurla Complex (BKC)53 km
Chhatrapati Shivaji Int'l Airport54 km
Nariman Point / Fort55 km
Lower Parel / Worli business district55 km
Andheri MIDC / SEEPZ55 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Karjat

Dhanlaxmi Heights
possession by Sep 2026 · Dhanlaxmi Developers
Warai Woods Ph 2
Not filing quarterly progress reports · possession by Nov 2026 · Nahar Riddhi Siddhi Developers
Jambrung Valley
possession by Nov 2026 · Kirtiraj Nanasaheb Sawant
Bliss Studio
possession by Dec 2026 · Balsam Builders
Beverly Hills
possession by Dec 2026 · Rudram Infra Projects Private Limited
Jupiter Heights
Not filing quarterly progress reports · possession by Dec 2026 · Jupiter Heights

Major developers building in Karjat

Other RERA-registered projects in Raigarh

Shiv Complex Building
declared completion May 2023 · Laxmi Developers
Shiv Datta Darshan
possession by Dec 2027 · Hezal AND Navya Infra LLP
Shiv Dham
declared completion Dec 2022 · Shiv Buildcon
Shiv Elite
possession by Dec 2026 · Premji Dosha Vaviya
Shiv Emerald
possession by Dec 2026 · Shivkrupa Builders & Developers
Shiv Empire
possession by Dec 2027 · B N Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026