SHIV PARVATI COMPLEX

Mumbai Suburban · LINKPROMOTERS & POKAR ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800005290

Delivery and registration

When is the project declared for completion?

SHIV PARVATI COMPLEX is registered with MahaRERA as P51800005290 and the promoter has declared completion for 31 Mar 2019.

31 Mar 2019

declared completion

90months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800005290
Registered on11 Aug 2017
Promoter-declared completion31 Mar 2019
Current statusCertificate Signed
Against todayabout 90 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHIV PARVATI COMPLEX record 7 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 7 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHIV PARVATI COMPLEX in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
SHIV PARVATI COMPLEX1G+8-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for SHIV PARVATI COMPLEX, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000000166708/11/2017MAHENDRA D BHANUSHALI vs LINK PROMOTERS AND POKAR ENTERPRISESorder passed

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400084. Per the filed land record, the plot is bounded to the north by 18 30 mt road, to the south by 313 315 plot C, to the east by 18 30 mt road and to the west by CTS No 314. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Powai / Hiranandani business park3 km
Chhatrapati Shivaji Int'l Airport3 km
Bandra Kurla Complex (BKC)4 km
Andheri MIDC / SEEPZ5 km
Lower Parel / Worli business district13 km
Nariman Point / Fort20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ghatkopar West

Anusaya
possession by Jun 2027 · Satre Infrastructure Pvt. Ltd.
Neumec Srushti
possession by Dec 2027 · Neumec Estate Developer LLP
Rajanigandha Cottage CO-Operative Housing Society LTD
possession by Dec 2029 · Jyoti Real-Tech Private Limited
Ganeshwadi CHS LTD - S.r.a
declared completion Dec 2023 · Ashok Rajaram Gupta
Chintamani Glory
declared completion Jun 2022 · Chintamani Realty
Jhelum
declared completion Dec 2021 · Satre Infrastructure Private Limited

Other RERA-registered projects in Mumbai Suburban

Shiv Sagar Enclave
declared completion Dec 2022 · Shiv Enclave Corporation
Shiv Samarth
declared completion Dec 2024 · Aakruti Enterprises
Shiv Shakti Chsl
declared completion Mar 2026 · Amar Associates
Shiv Shreyas Chsl
declared completion Dec 2025 · K P Developers
Shiv Shubharambh
declared completion Mar 2024 · Navkarmik Infra & Development Privat
Shiv Sneh
possession by May 2029 · Navkarmik Landspaces LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026