Mumbai/Project record

MahaRERA · the public record

SHIV SAI COMPLEX

TAL KARJAT · SHIV SAI DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

74units filed as unsoldInventory · 17 September 2026
31 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
131registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000015737

Delivery and registration

When is the project declared for completion?

SHIV SAI COMPLEX is registered with MahaRERA as P52000015737 and the promoter has declared completion for 31 Dec 2026.

31 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000015737
Registered on19 Mar 2018
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHIV SAI COMPLEX record 33 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 33 quarterly progress reports on record since registration, with no current default.

Sales

How much has actually been sold?

In SHIV SAI COMPLEX, 7 of 81 homes filed with MahaRERA are recorded as sold or booked (6 with registered agreements and 1 booked), about 9%, and 74 remain available.

9%sold

7 of 81 homes

₹1.07 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹75.05 Lakh (about 70%) is recorded as collected and ₹31.95 Lakh as receivable. The project registers 131 homes in total, while this sold/unsold inventory filing covers 81 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 7 registered agreements, the effective carpet rate is ₹3,526/sqft, with eight in ten falling between ₹2,123 and ₹5,661 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The inventory filing also declares: 50 owner/investor-held.

What the filings record, home by home

Read from MahaRERA on 17 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 7 homes carry one, and 74 of the 131 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
F-203380 sqftRs 10.00 lakh to Rs 10.50 lakh2 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In SHIV SAI COMPLEX, 4 of the 74 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 73 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 131 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
BUILDING NO 1-B WING1G+511-
BUILDING NO 4 - H WING1G+512-
BUILDING NO 3 - G WING1G+424-
BUILDING NO 3 - F WING1G+721-
BUILDING NO 2 - E WING1G+521-
BUILDING NO 2 - D WING1G+521-
BUILDING NO 2 - C WING1G+621-

Unit mix on the filing: 98 residential and 33 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered29 Dec 2024Our Project is almost complete. We just need Extension till 29-12-2024.
29 Dec 202431 Mar 2026We have details mentioned how we can complete our project till 31-03-2026
31 Mar 202631 Dec 20261) Poor booking response from customer. 2) Because of poor response our work was very slow. 3) Delay from getting Electric Transformer from Government Authority.

Location, Land & Connectivity

Located at TAL KARJAT, VILLAGE CHINCHAVALI, Thane, Thane, 410201. Per the filed land record, the plot is bounded to the north by SURVEY 7-1, to the south by SURVEY 7-6, to the east by SURVEY 7-7A and to the west by ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~48 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park48 km
Andheri MIDC / SEEPZ49 km
Chhatrapati Shivaji Int'l Airport53 km
Bandra Kurla Complex (BKC)55 km
Lower Parel / Worli business district64 km
Nariman Point / Fort71 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shiv SAI Developers is the promoter on 8 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Shiv SAI Developers project & its RERA track record →

Other flagged projects by Shiv SAI Developers

Shiv SAI Developers
FlaggedPalghar
Shiv SAI Developers
FlaggedPalghar

Other RERA-registered projects in Karjat

Dhanlaxmi Heights
possession by Sep 2026 · Dhanlaxmi Developers
Warai Woods Ph 2
Not filing quarterly progress reports · possession by Nov 2026 · Nahar Riddhi Siddhi Developers
Jambrung Valley
possession by Nov 2026 · Kirtiraj Nanasaheb Sawant
Bliss Studio
possession by Dec 2026 · Balsam Builders
Beverly Hills
possession by Dec 2026 · Rudram Infra Projects Private Limited
Jupiter Heights
Not filing quarterly progress reports · possession by Dec 2026 · Jupiter Heights

Major developers building in Karjat

Other RERA-registered projects in Raigarh

Shiv Samarth
declared completion May 2026 · Manoj Omprakash Jaiswal
Shiv Samarth Enclave
declared completion Jun 2026 · Patil Infracon Private Limited
Shiv Shakti Complex
possession by Dec 2028 · Shiv Shakti Developers
Shiv Shalini Complex
possession by Dec 2028 · Ganarai Developers
Shiv Shankar Ashirwad
declared completion Jun 2022 · Suresh Shivshankar Sharma
Shiv Shankar Residency
possession by Dec 2026 · Suresh Shivshankar Sharma

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026