SHIVA, SHIVAKARI, SATYA

Mumbai Suburban · Shree Mahalaxmi Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000003294

Delivery and registration

When is the project declared for completion?

SHIVA, SHIVAKARI, SATYA is registered with MahaRERA as P52000003294 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000003294
Registered on05 Aug 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHIVA, SHIVAKARI, SATYA record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 26 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHIVA, SHIVAKARI, SATYA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2.

BuildingWingsFloorsDeclared completion
SHIVA1G+2-
SHIVKARI1G+2-
SATYA1G+2-

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for SHIVA, SHIVAKARI, SATYA, with orders passed in 4 of them.

5complaints

4with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000007899121/04/2019Vijay Madhavrao Sonar vs Shree Mahalaxmi Developersorder passed
CC00600000021050723/03/2022Amol Anil Naik vs Parag Thakkar/ Shilpa Parag Thakkarorder passed
CC00600000023119216/06/2022ShailendraSingh GaneshSingh Thakur vs PARAG PANKAJ THAKKAR, SHILPA PARAG THAKKARorder passed
CC1250368916/10/2025dan aravin mathiah vs Shree Mahalaxmi Developersorder passed
CC1260016910/01/2026Murali Parayar vs Shree Mahalaxmi Developerspending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2023Due to medical reason

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 410101. Per the filed land record, the plot is bounded to the north by Survey No 67, to the south by Survey No 67, to the east by Survey No 67 and to the west by Survey No 67. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~48 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park48 km
Bandra Kurla Complex (BKC)51 km
Chhatrapati Shivaji Int'l Airport51 km
Andheri MIDC / SEEPZ52 km
Lower Parel / Worli business district55 km
Nariman Point / Fort57 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shree Mahalaxmi Developers is the promoter on 10 MahaRERA-registered projects, of which 10 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Shree Mahalaxmi Developers project & its RERA track record →

Other flagged projects by Shree Mahalaxmi Developers

Shree Mahalaxmi Developers
Past its declared completion dateRaigarh
Shree Mahalaxmi Developers
Past its declared completion dateRaigarh
Shree Mahalaxmi Developers
Past its declared completion dateRaigarh
Shree Mahalaxmi Developers
Past its declared completion dateRaigarh
Shree Mahalaxmi Developers
Past its declared completion dateRaigarh
Shree Mahalaxmi Developers
Past its declared completion dateRaigarh

Other RERA-registered projects in Neral

Arsh Apartment
possession by Sep 2026 · Mateen Rafique Patel
Naaz Plaza
possession by Sep 2026 · Prestige Reality
Labdhi Gardens Phase 6
possession by Dec 2026 · Labdhi Lifestyle Limited
Labdhi Gardens Phase 7
possession by Dec 2026 · Labdhi Lifestyle Limited
Labdhi Gardens Phase 8
possession by Dec 2026 · Labdhi Lifestyle Limited
RAJ Baug Phase - III
possession by Dec 2026 · Nehaldhara Realtors

Major developers building in Neral

Other RERA-registered projects in Raigarh

Shivalay
declared completion Jan 2026 · Buildrite Realtors
Shivalik Aura
declared completion Dec 2023 · Mukesh Shrinath Sharma
Shivam
declared completion Aug 2024 · Hareshkumar Rasiklal Shah
Shivam
declared completion Jun 2026 · Sarch Properties Private Limited
Shivam Apartment
declared completion Mar 2023 · Shanti Developers
Shivam Apartment
declared completion Sep 2023 · MAA Shitaladevi Realty

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026