SHIVTEJ ASHIYANA

Nerul · YOGESH RAMDAS SARJINE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

15units filed as unsoldInventory · 16 September 2026
31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700011753

Delivery and registration

When is the project declared for completion?

SHIVTEJ ASHIYANA is registered with MahaRERA as P51700011753 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700011753
Registered on31 Aug 2017
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHIVTEJ ASHIYANA record 34 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Yogesh Ramdas Sarjine is the promoter of record on 3 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

What the filings record, home by home

Read from MahaRERA on 16 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 13 homes carry one, and 15 of the 28 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
103441 sqftRs 47.80 lakh typical, over Rs 47.00 lakh to Rs 59.00 lakh4 filed on this stack, floors 2–5

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In SHIVTEJ ASHIYANA, 7 of the 15 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 14 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
SHIVTEJ ASHIYANA1G+831 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2019We have already applied for NOC from CIDCO and completion certificate to NMMC Authority, but NOC from CIDCO is still awaited. Hence completion certificate is also not received till
30 Apr 201931 Dec 2020Building Construction is already completed. No Dues Certificate is awaited from CIDCO to submit to NMMC for Occupancy Certificate.
31 Dec 202031 Dec 2025In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various r

Location, Land & Connectivity

Located at Nerul, Thane, Thane, 400706. Per the filed land record, the plot is bounded to the north by 9 MT WIDE ROAD, to the south by PLOT NO 106 A, to the east by PLOT NO 105B and to the west by PLOT NO 105. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~20 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park20 km
Bandra Kurla Complex (BKC)22 km
Chhatrapati Shivaji Int'l Airport23 km
Andheri MIDC / SEEPZ24 km
Lower Parel / Worli business district25 km
Nariman Point / Fort28 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Yogesh Ramdas Sarjine is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Nerul

Cyber Code
possession by Sep 2026 · Greenscape Realty
Shreeji Dios
possession by Dec 2026 · Shreeji Ventures Nirmaan Private Limited
Infinity Ikon
possession by Dec 2026 · Emperia Projects
Plan I
possession by Dec 2026 · M/s. Tescon Plan-I LLP
Regency Palms Phase IV
possession by Dec 2026 · Regency INC
Sawan Serenity
possession by Dec 2026 · Shree Sawan Buildcon

Other RERA-registered projects in Thane

Shivtirth
possession by Dec 2027 · Mangalya Reality
Shlok Apartment
declared completion Dec 2025 · Chetan Abhimanyu Patil
Shobhana CO-Operative Housing Society LTD
declared completion Dec 2022 · Padmanabh Developers
Shon Heights
declared completion Dec 2024 · Green Homes Construction Company
Shraddha Peninsula
possession by Dec 2026 · Padmagriha Heights
Shram Safal CO-Operative Housing Society LTD
possession by May 2029 · Adeshwar Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026