MahaRERA Property Intelligence · Palghar

SHREE BALAJI HEAVEN

P99000047099 · BOISAR EAST · promoter Shree Balaji Homes

Certificate SignedDue 31 Mar 2026

Delivery & Registration

MahaRERA registrationP99000047099
Registered on03 Oct 2022
Promoter-declared completion31 Mar 2026
Current statusCertificate Signed
Against todayabout 4 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
SHREE BALAJI HEAVEN 6B1G+731 Mar 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at BOISAR EAST, CHILLER ROAD, Palghar, Palghar, 401501. Per the filed land record, the plot is bounded to the north by ROOP RAJAT BUILDING, to the south by OPEN LAND RESERVE FOR SCHOOL, to the east by 5A AND 5B BUILDING and to the west by OPEN LAND. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~64 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ64 km
Powai / Hiranandani business park66 km
Chhatrapati Shivaji Int'l Airport68 km
Bandra Kurla Complex (BKC)71 km
Lower Parel / Worli business district78 km
Nariman Point / Fort86 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shree Balaji Homes is the promoter on 3 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Shree Balaji Homes

Shree Balaji Homes
Past its declared completion dateThane

Other RERA-registered projects in Boisar

Ostwal Dream Land Phase - II
possession by Jul 2026 · Shree Ostwal Builders LTD
Parvati Homes
possession by Jul 2026 · Iconic Developers
Queens Villa
possession by Jul 2026 · Shashi Kuldeep Ostwal
Classic Apartment
possession by Sep 2026 · I.k.group
Divyajal
possession by Sep 2026 · Divyaraj Properties LLP
Kinjal Complex II
possession by Sep 2026 · Kinjal Enterprises

Major developers building in Boisar

Other RERA-registered projects in Palghar

Shree Balaji Paradise
declared completion Dec 2024 · Shree Balaji Projects
Shree Balaji Pride Building NO 01
possession by Dec 2027 · Shree Balaji Affordable Homes
Shree Balaji Pristine
possession by Dec 2031 · Shree Narayana Projects
Shree Balaji Residency
declared completion Jun 2023 · Shree Balaji Enterprises
Shree Ballal Vinayak
possession by Dec 2026 · Sneha Builders AND Developers
Shree Balram
declared completion May 2019 · Sweet Home Realtors

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026