SHREE GANESH RESEDENCY

KARJAT · ARTH INFRA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000022105

Delivery and registration

When is the project declared for completion?

SHREE GANESH RESEDENCY is registered with MahaRERA as P52000022105 and the promoter has declared completion for 30 Jun 2024.

30 Jun 2024

declared completion

27months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000022105
Registered on27 Aug 2019
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 27 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHREE GANESH RESEDENCY record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHREE GANESH RESEDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
SHREE GANESH RESEDENCY1G+331 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2022DUE TO COVID 19 THE LABOR WORK WAS ON HALT AND SHORTAGE OF LABOUR WE WERE UNABLE TO COMPLETE THE PROJECT ON TIMELINE. WE WOULD REQUEST THE AUTHORITY TO GRANT US FURTHER EXTENSION O
30 Dec 202231 Dec 2023SINCE ADDITIONAL FSI MADE AVAILABLE, PLAN AS BEEN REVISED BEFORE BUILDING WAS G+3, NOW REVISED PLAN SECTION ON 13/02/2023 NOW WE GOT GR+4 APPROVED ,SO REQUEST U TO GENERATE NEW C
31 Dec 202330 Jun 2024SAID PROJECT AS COMPLETED 95% WORK, HOWEVER SINCE ADDITIONAL FSI MADE AVAILABLE TO US CONSEQUENTLY MODIFIED PLAN HAVE BEEN SUBMITTED FOR EXPLOITATION OF ADDITIONAL FSI THE SCHUDE

Location, Land & Connectivity

Located at KARJAT, DEOLUWADI, Kurla, Mumbai Suburban, 410210. Per the filed land record, the plot is bounded to the north by ROAD, to the south by 61, to the east by ROAD and to the west by ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kharghar

Tharwani Palladian
possession by Sep 2026 · Tharwani Realtors
Balaji Park
possession by Oct 2026 · Mohansingh Tararam Choudhary
Krishna Aura
possession by Oct 2026 · Qualitas Lifespaces LLP
Ashwini Apartment
possession by Dec 2026 · Kuldeepsingh Amarsingh Bhalothia
Bhagwati Luxuria
possession by Dec 2026 · Bhagwati Signature LLP
Elysian
possession by Dec 2026 · Devam Ventures

Major developers building in Kharghar

Other RERA-registered projects in Raigarh

Shree Ganesh Residency
possession by Jun 2027 · Arth Realtors
Shree Ganesh Residency
declared completion Jun 2025 · M G Construction
Shree Ganesh Residency
possession by Jun 2028 · RAJ Homes
Shree Ganpati
declared completion Jun 2024 · Shree Ganpati Developers
Shree Gatha Residency
possession by Dec 2032 · Shree Builders AND Developers
Shree Guru Ashish CO OP HSG Society LTD
declared completion Sep 2025 · WE Grow Constructions

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.