MahaRERA Property Intelligence · Mumbai Suburban

SHREE GOHIL MANSION CO OP HOUSING SOCIETY LTD

P51800009541 · promoter Vidisha Real Estate

Certificate SignedDue 30 Jun 2019

Delivery & Registration

MahaRERA registrationP51800009541
Registered on22 Aug 2017
Promoter-declared completion30 Jun 2019
Current statusCertificate Signed
Against todayabout 85 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Vidisha Real Estate is the promoter of record on 6 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
SHREE GOHIL MANSION CO OP HOUSING SOCIETY LTD A WING1G+1430 Jun 2019
SHREE GOHIL MANSION CO OP HOUSING SOCIETY LTD WING B1G+1430 Jun 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 201930 Jun 2019The delay was due to no electric cable availability by Reliance and labour problem in the month of April and May and thus the project has not received the Occupancy Certificate ( O

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 400067. Per the filed land record, the plot is bounded to the north by CTS 261 AND 263, to the south by CTS NO 265, to the east by BY CTS NO 264 and to the west by SHANTILAL MODI CROSS ROAD NO 2. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ8 km
Powai / Hiranandani business park11 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)15 km
Lower Parel / Worli business district23 km
Nariman Point / Fort31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Vidisha Real Estate Developers PVT LTD is the promoter on 4 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Vidisha Real Estate Developers PVT LTD

Vidisha Real Estate Developers PVT LTD
FlaggedMumbai Suburban
Vidisha Real Estate Developers PVT LTD
FlaggedMumbai Suburban
Vidisha Real Estate Developers PVT LTD
FlaggedMumbai Suburban

Other RERA-registered projects in Kandivali West

Primrose
possession by Jul 2026 · Kaustubh Construction Private Limited
Harmony
possession by Aug 2026 · Shreenath Associates
Laxmi Heights
possession by Sep 2026 · M/S Laxmi Lifespaces
Mahavir Majesty
possession by Sep 2026 · Mahavir Builders
Neelam CHS LTD
possession by Sep 2026 · Sapriya Developers
Alok
possession by Sep 2026 · Shree Dhanesh Buildcon

Major developers building in Kandivali West

Other RERA-registered projects in Mumbai Suburban

Shree Gopal
possession by Apr 2028 · Dipti Builders Universal Pvt Ltd
Shree Gopaldham
possession by Dec 2030 · JE AND VEE Loksun Developers
Shree Govind Krupa
declared completion Jun 2026 · Mamtora Foundation
Shree Hari Enclave
declared completion Dec 2025 · Paresh Harilal Patel
Shree Hari Krupa
possession by Sep 2026 · Mamtora Foundation
Shree Hari OM Nagar
possession by Dec 2027 · Rising Pioneers Infra LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026