MahaRERA Property Intelligence · Raigarh

SHREE JOGESHWARI RESIDENCY

P52000024302 · BAZARPETH · promoter Shree Jogeshwari Residency

Certificate SignedDue 30 Mar 2022

Delivery & Registration

MahaRERA registrationP52000024302
Registered on03 Feb 2020
Promoter-declared completion30 Mar 2022
Current statusCertificate Signed
Against todayabout 52 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shree Jogeshwari Residency is the promoter of record on 4 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
BUILDINGA1G+531 Mar 2021
BUILDINGB1G+531 Mar 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Roha98/20162016Hearing Is O Progress

Location, Land & Connectivity

Located at BAZARPETH, -, Roha, Raigarh, 402106. Per the filed land record, the plot is bounded to the north by GRAMPANCHAYAT ROAD, to the south by RAIN WATER NALA, to the east by PARDI NO 26B and to the west by PARDI NO 23. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nagothane

Bhide Residency
possession by Dec 2026 · Gopikrishna Constrcution
MAN Saroj Plaza
possession by Jun 2027 · Not Available
Morya Home Town
possession by Dec 2027 · Morya Infraconstruct Private Limited
OM Sneh Prabha Complex
possession by Dec 2027 · Sanjay Ramchandra Dalavi
Zuha Park
possession by Dec 2027 · Jaleel Ahmad Patel
Amba Residency
possession by Dec 2028 · N R Builders And Developers

Other RERA-registered projects in Raigarh

Shree Karu Mata Niwas
declared completion Dec 2022 · Manoj Omprakash Jaiswal
Shree Krishna Kashtbhanjan
possession by Dec 2029 · Chambaria Enterprises
Shree Krishna Residency
possession by Dec 2027 · SAI Prasad Enterprises
Shree Krupa
declared completion Dec 2017 · Shree Ganesh Developers
Shree Krupa
declared completion Dec 2022 · Vihaan Developers
Shree Krupa
possession by Dec 2026 · Shree Yashaswin Realtors

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026