01 Apr 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

01 Apr 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700027633

Delivery and registration

When is the project declared for completion?

SHREE KRISHNA INFRA is registered with MahaRERA as P51700027633 and the promoter has declared completion for 01 Apr 2026.

01 Apr 2026

declared completion

5months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700027633
Registered on25 Dec 2020
Promoter-declared completion01 Apr 2026
Current statusCertificate Signed
Against todayabout 5 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHREE KRISHNA INFRA record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHREE KRISHNA INFRA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
SHIV ASHIRWAD1G+1201 Oct 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at -, VILLAGE THAKURLI, Kalyan, Thane, 421202. Per the filed land record, the plot is bounded to the north by BUILDING, to the south by ROAD, to the east by SCHOOL and to the west by ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dombivli West

Amar Elegance
possession by Sep 2026 · Amar Realty
Purva Prime
possession by Sep 2026 · Trimurti Constructions
Anant AND Radhika Heights
possession by Dec 2026 · Ashapura Construction CO
Chintamani Heights & Chintamani Kuber
possession by Dec 2026 · Chintamani Developers
Indira Galaxy
possession by Dec 2026 · Shree Developers
Jai Shree Ganesh Co-Operative Housing Society Limited
possession by Dec 2026 · Shree Vyankatesh Enterprises

Major developers building in Dombivli West

Other RERA-registered projects in Thane

Shree Krishna Kunj
declared completion May 2026 · Bhagwati Builders AND Developers
Shree Krishna Kunj CO-OP HSG SOC LTD
possession by Dec 2026 · Infinity Infra
Shree Krishna Towers
declared completion Dec 2024 · Shukla Construction
Shree Krupa
possession by Dec 2027 · Magnum Builders
Shree Krupa Apartment
declared completion Dec 2018 · Vastu Developers
Shree Krupa CO OP Housing Society
possession by Sep 2026 · Sharda Vastu Nirmitee Pvt. Ltd.

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.