Shree Madhusudan CHSL

P51800005040 · promoter Spark Builders Infra

Certificate SignedDue 31 Dec 2018

Delivery & Registration

MahaRERA registrationP51800005040
Registered on09 Aug 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 91 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Spark Builders Infra is the promoter of record on 9 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Shree Madhusudan CHSL1G+8-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 201831 Dec 2018PR CARD APPLICATION IS IN PROECESS WITH THE CITY SURVEY OFFICE AT BANDRA EAST SINCE MARCH 2017 AND ONLY THIS COMPLIANCE IS PENDING TO OBTAIN FULL OC TO OUR PROJECT.

Location, Land & Connectivity

Located at Mumbai City, Mumbai City, 400057. Per the filed land record, the plot is bounded to the north by Visawa Bldg, to the south by Om Madhusudan CHSL, to the east by Medini CHSL and to the west by Play ground Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport2 km
Andheri MIDC / SEEPZ4 km
Bandra Kurla Complex (BKC)5 km
Powai / Hiranandani business park6 km
Lower Parel / Worli business district12 km
Nariman Point / Fort20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vile Parle East

Vidyalankar Chsl
possession by Jul 2026 · Desai Residency Private Limited
Viva Dhanlaxmi
possession by Aug 2026 · Y K & Sons Mumbai
Parkway Manor
possession by Aug 2026 · Gautam Ekanath Thakur
Sandeep Ankur Residency
possession by Aug 2026 · Anusri Enterprises LLP
Moti Madhav
possession by Sep 2026 · Aadhya Skyvista
Neumec Niwara
possession by Sep 2026 · Neumec Venture

Major developers building in Vile Parle East

Other RERA-registered projects in Mumbai Suburban

Shree Madhuvandham
declared completion Dec 2022 · Sunder Corporation
Shree Mahalakshmi Kunj
possession by Dec 2026 · Shree Mahalakshmi Constructions
Shree Mahalakshmi Saburi
possession by May 2027 · Shree Mahalakshmi Constructions
Shree Mangal
declared completion Dec 2017 · Mangal Buildhome Private Limited
Shree Manik Vishwa
declared completion Jun 2026 · Anil Gangaram Sawant
Shree Matru Krupa
possession by Mar 2028 · Shree Bharani Projects LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026