SHREE RAMCHANDRA RESIDENCY PHASE II

Roha · CRK INFRASTRUCTURE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Mar 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Mar 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000029169

Delivery and registration

When is the project declared for completion?

SHREE RAMCHANDRA RESIDENCY PHASE II is registered with MahaRERA as P52000029169 and the promoter has declared completion for 30 Mar 2024.

30 Mar 2024

declared completion

30months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000029169
Registered on03 May 2021
Promoter-declared completion30 Mar 2024
Current statusCertificate Signed
Against todayabout 30 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHREE RAMCHANDRA RESIDENCY PHASE II record 12 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 12 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHREE RAMCHANDRA RESIDENCY PHASE II in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
SHREE RAMCHANDRA RESIDENCY PHASE II BUILDING A1G+331 Mar 2023
SHREE RAMCHANDRA RESIDENCY PHASE II BUILDING B1G+431 Mar 2023
SHREE RAMCHANDRA RESIDENCY PHASE II BUILDING D1G+431 Mar 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Mar 2024This is to bring to your notice that the project is 80% completed, and we have also in process to complete the project and to apply for oc but we have some unsold units which needs

Location, Land & Connectivity

Located at Roha, Bhuwaneshwar, Varse, Roha, Roha, Raigarh, 402116. Per the filed land record, the plot is bounded to the north by SURVEY NO 21 HISSA NO 3D 3B 4B, to the south by SURVEY NO 37, to the east by Road and to the west by SURVEY NO 21 HISSA NO 3B 4B. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

CRK Infrastructure is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Roha

Nirmala Park
possession by Apr 2027 · Cyril Duming Dsouza
Arise Arcade
possession by Dec 2027 · Arise Developers
Chandradarshan Heights Phase III
possession by Dec 2027 · Tatvaraj Developers
OM Shanti Heights
possession by Dec 2027 · Mahboob Abbasali Khan
Wing B Of Delta Heights
Not filing quarterly progress reports · possession by Mar 2028 · Shree Hari Builders & Developers
Narmada Nirman Housing Complex
possession by Jul 2028 · Shreekrupa Realtors Private Limited

Other RERA-registered projects in Raigarh

Shree Residency
declared completion Dec 2021 · Shreeji Enterprises
Shree Residency
declared completion Dec 2023 · Vibrant Group
Shree Sadan
declared completion Dec 2019 · Supcon Developers Private Limited
Shree Sadguru Complex Building - 5
possession by Jun 2027 · Earth Home
Shree Sadguru Complex - Phase III
declared completion Dec 2021 · Earth Home
Shree Sadguru Complex - Phase IV
declared completion Dec 2022 · Earth Home

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.