Mumbai/Project record

MahaRERA · the public record

SHREE SADGURU PARK

PEN · SAFAL DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

111units filed as unsoldInventory · 20 September 2026
31 Aug 2027declared completionMahaRERA registration · read 12 Jul 2026
168registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Aug 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000078114

Delivery and registration

When is the project declared for completion?

SHREE SADGURU PARK is registered with MahaRERA as P52000078114 and the promoter has declared completion for 31 Aug 2027.

31 Aug 2027

declared completion

11months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000078114
Registered on25 Nov 2024
Promoter-declared completion31 Aug 2027
Current statusCertificate Signed
Against today11 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHREE SADGURU PARK record 4 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 4 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Safal Developers is the promoter of record on 9 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

9projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In SHREE SADGURU PARK, ₹6.84 Cr of a declared ₹27.60 Cr estimated project cost is reported as incurred, about 24.8%, as at the last certified filing with MahaRERA.

24.8%

₹6.84 Cr

of ₹27.60 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In SHREE SADGURU PARK, 46 of 168 homes filed with MahaRERA are recorded as sold or booked (10 with registered agreements and 36 booked), about 27%, and 122 remain available.

27%sold

46 of 168 homes

₹9.86 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹1.53 Cr (about 16%) is recorded as collected and ₹8.33 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 46 registered agreements, the effective carpet rate is ₹5,952/sqft, with eight in ten falling between ₹3,196 and ₹6,649 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 20 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 57 homes carry one, and 111 of the 168 are recorded unsold. Since we started watching this ledger, 11 homes have moved out of the unsold list, most recently on 11 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
B-105379 sqftRs 5,925 a sq ft typical, over Rs 3,196 to Rs 6,41021 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In SHREE SADGURU PARK, 81 of the 111 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 110 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6 and 168 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
A WING1G+635-
B WING1G+649-
C WING1G+642-
D WING1G+642-

Unit mix on the filing: 154 residential and 14 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at PEN , AT PEN , Thane, Thane, 402107. Per the filed land record, the plot is bounded to the north by 9 MTR WIDE ROAD AND SURVEY NO 265A, to the south by SURVEY NO 272A-4-5-6, to the east by 9 MTR WIDE ROAD AND SURVEY NO 272-3-1PT and to the west by SURVEY NO 270 272A AND272-6. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Pen

Pendse Park
possession by Nov 2026 · F ND H Constructions
Govardhan Greenfields
possession by Dec 2026 · Khelaan Manoj Unadkat
Balaji Tricity
possession by Dec 2026 · M/s Sathe Schemes
Arham
possession by Dec 2026 · IYS Properties LLP
Chandradarshan Enclave
Not filing quarterly progress reports · possession by Dec 2026 · Sunny Rajendra Jain
Kalindi Elite
possession by Dec 2026 · Kalindi Realtors Private Limited

Other RERA-registered projects in Raigarh

Shree Sadguru Residency
declared completion Dec 2022 · Milestone Construction
Shree Sahayya Prime
possession by Dec 2028 · Shree Sahayya Group
Shree Sai
declared completion Jun 2021 · Saras Associates
Shree SAI
declared completion Mar 2022 · Mahesh Krishna Gowari
Shree SAI Apartment
declared completion Aug 2022 · S K Developers
Shree SAI Apartment
declared completion Mar 2022 · Dattatrya Malikarajun Sagar

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026