MahaRERA Property Intelligence · Palghar

SHREE SAI DARSHAN

P99000052942 · NAVALI · promoter Imperia

Certificate SignedDue 30 Jun 2027

Delivery & Registration

MahaRERA registrationP99000052942
Registered on05 Oct 2023
Promoter-declared completion30 Jun 2027
Current statusCertificate Signed
Against today11 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Construction Progress

MahaRERA's cost filing puts construction at ~62.2% of the estimated project cost incurred as of the last certificate (₹95.58 Lakh spent against a ₹1.54 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 21 homes filed with MahaRERA, 15 are sold/booked (11 with registered agreements + 4 booked) and 6 remain available (~71% sold) — selling steadily. Buyers have committed ₹2.11 Cr in agreement value so far. Of that, ₹90.52 Lakh (~43%) is already collected, ₹1.20 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 15 registered agreements, the effective carpet rate is ₹6,545/sqft (typical range ₹4,800–₹7,981) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 3303188 sqft (17.46 sqm)₹9.56 Lakh
Floor 4402236 sqft (21.9 sqm)₹11.32 Lakh
Floor 5502236 sqft (21.9 sqm)₹11.32 Lakh
Floor 5503188 sqft (17.46 sqm)₹9.56 Lakh
Floor 7702236 sqft (21.9 sqm)₹11.32 Lakh
Floor 7703188 sqft (17.46 sqm)₹9.56 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 21 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
SHREE SAI DARSHAN1G+72131 Dec 2025

Unit mix on the filing: 21 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202530 Jun 2027Shortage of Funds due to low demand: The real estate project, situated in a remote area, has faced significant challenges due to limited customer bookings, resulting in a lower-th

Location, Land & Connectivity

Located at NAVALI, NA, Palghar, Palghar, 401404. Per the filed land record, the plot is bounded to the north by SURVEY NO 25-1-A PLOT NO 44 AND 37, to the south by SURVEY NO 25-1-A PLOT NO 43, to the east by 6 METERS WIDE ROAD and to the west by SURVEY NO 25-1-A PLOT NO 38. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~63 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ63 km
Powai / Hiranandani business park65 km
Chhatrapati Shivaji Int'l Airport67 km
Bandra Kurla Complex (BKC)70 km
Lower Parel / Worli business district77 km
Nariman Point / Fort85 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every Imperial Infrarealty Private Limited project & its RERA track record →

Other RERA-registered projects in Palghar

Shree SAI Apartment
possession by Jul 2026 · Shree SAI Jivdani Developers
Madhav Vatika - VI
possession by Jul 2026 · R M N H Developers LLP
Prithvi Anand Kuber Complex
possession by Jul 2026 · Prithvi Anand Housing And Land Developer
Vardhaman Divine
possession by Jul 2026 · Vardhaman AND Shah Associates
Symphony Heights
possession by Aug 2026 · Kreate Space LLP
Shree Puram - 2, Building No. 1
possession by Aug 2026 · Vastu Realities

Major developers building in Palghar

Other RERA-registered projects in Palghar

Shree Sai Residential Park
possession by Dec 2026 · Laxmi Associates
Shree SAI Sadan
declared completion Dec 2025 · M.r.builders AND Developers
Shree Saket
declared completion Dec 2025 · Novel Build-CON
Shree Salasar ROW Villas
possession by Dec 2029 · Dilip Enterprises
Shree Salasar ROW Villas
possession by Jan 2028 · Radha Krishna Realty
Shree Samarth Building
possession by Jun 2030 · Shree Swami Samarth Realtors

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026