Shree Sai Dhan Residency

Pen · SAI SHRADDHA SAI BUILDERS AND DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000015791

Delivery and registration

When is the project declared for completion?

Shree Sai Dhan Residency is registered with MahaRERA as P52000015791 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000015791
Registered on26 Mar 2018
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Shree Sai Dhan Residency record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 24 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sai Shraddha Sai is the promoter of record on 124 projects registered with MahaRERA, 12 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

124projects

registered with MahaRERA

12flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Shree Sai Dhan Residency in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Shree Sai Dhan1G+531 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Pen, Near Nandimal Naka, Thane, Thane, 402107. Per the filed land record, the plot is bounded to the north by NA Plot No3 of Shri Prakash Patil, to the south by Aadivashi Prakalpa Building of Plot No1, to the east by Pen Dhavte D P Road and to the west by Survey No280 Hissa No3 ofShri Vitthal Laxman Chava. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~40 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort35 km
Lower Parel / Worli business district40 km
Bandra Kurla Complex (BKC)44 km
Chhatrapati Shivaji Int'l Airport46 km
Powai / Hiranandani business park47 km
Andheri MIDC / SEEPZ50 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Pen

Pendse Park
possession by Nov 2026 · F ND H Constructions
Govardhan Greenfields
possession by Dec 2026 · Khelaan Manoj Unadkat
Balaji Tricity
possession by Dec 2026 · M/s Sathe Schemes
Arham
possession by Dec 2026 · IYS Properties LLP
Chandradarshan Enclave
Not filing quarterly progress reports · possession by Dec 2026 · Sunny Rajendra Jain
Kalindi Elite
possession by Dec 2026 · Kalindi Realtors Private Limited

Other RERA-registered projects in Raigarh

Shree SAI Residency
possession by Dec 2029 · Shree SAI Developers
Shree SAI Shambu
possession by May 2027 · Sameer Lalchand Mhatre
Shree SAI Srushti Paradise
declared completion Jun 2023 · Arun Ramesh Tamboli
Shree Samarth Krupa
declared completion Dec 2022 · Manohar Hiraji Patil
Shree Samarth Krupa A/B Wing
declared completion Jun 2025 · Rajesh Shantaram Mahadik
Shree Samarth Krupa Apartment
possession by Dec 2028 · Sanjay Vithoba Kate

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.