SHREE SAMARTH HEIGHTS

NAVI MUMBAI · SAI KRUPA BUILDERS & DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700011658

Delivery and registration

When is the project declared for completion?

SHREE SAMARTH HEIGHTS is registered with MahaRERA as P51700011658 and the promoter has declared completion for 31 Dec 2019.

31 Dec 2019

declared completion

81months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700011658
Registered on31 Aug 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 81 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHREE SAMARTH HEIGHTS record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHREE SAMARTH HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+25.

BuildingWingsFloorsDeclared completion
SHREE SAMARTH HEIGHTS1G+25-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2019Since we could not complete by the said completion date. We want to extend the completion date to 31/12/2019.

Location, Land & Connectivity

Located at NAVI MUMBAI, PLOT NO 6 SECTOR 15, Thane, Thane, 400701. Per the filed land record, the plot is bounded to the north by PLOT NO 07, to the south by PLOT NO 05, to the east by S T P PLOT NO 03 and to the west by 8 MTR SERVICE ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park11 km
Andheri MIDC / SEEPZ15 km
Chhatrapati Shivaji Int'l Airport16 km
Bandra Kurla Complex (BKC)16 km
Lower Parel / Worli business district24 km
Nariman Point / Fort30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

SAI Krupa Builders & Developers is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Ghansoli

Alliaance Icon
possession by Dec 2026 · Satyam Infra
Gami Asters A Wing
possession by Dec 2026 · Thalia AND Gami Enterprises
Gami Asters B Wing
possession by Dec 2026 · Thalia AND Gami Enterprises
Kusum Residency
possession by Dec 2026 · Suresh Padman Patil
Goldcrest Residency - Phase 2
possession by Mar 2027 · Savita Homemakers LLP
Century TWO
possession by Mar 2028 · City Infra

Other RERA-registered projects in Thane

Shree Samarth Krupa Prasad CO Operative Housing Society Limited
declared completion Jun 2026 · Rajlaxmi Samarth Developers
Shree Samarth Paradise
possession by Dec 2028 · Shree Mangalmurti Developers
Shree Samarth Park
declared completion Jun 2023 · Shree Enterprises
Shree Samarth SAH-WAS CO-OP Hsg. Society Ltd., Anamika Building
declared completion Jun 2025 · Joshi Enterprises
Shree Sankalp
declared completion May 2023 · Vinod Kisan Mhatre
Shree Shankheshwar Ashish
possession by Dec 2026 · Rajaram Construction

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026