Mumbai/Project record

MahaRERA · the public record

SHREE SIDDHIVINAYAK PARK C1,C2,C3

MURBAD · SATYASHIV DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700024653

Delivery and registration

When is the project declared for completion?

SHREE SIDDHIVINAYAK PARK C1,C2,C3 is registered with MahaRERA as P51700024653 and the promoter has declared completion for 30 Dec 2026.

30 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700024653
Registered on26 Feb 2020
Promoter-declared completion30 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHREE SIDDHIVINAYAK PARK C1,C2,C3 record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Satyashiv Developers is the promoter of record on 4 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

4projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHREE SIDDHIVINAYAK PARK C1,C2,C3 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
SHREE SIDDHIVINAYAK PARK C11G+831 Dec 2025
SHREE SIDDHIVINAYAK PARK C21G+531 Dec 2025
SHREE SIDDHIVINAYAK PARK C31G+531 Dec 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at MURBAD, PLOT NO S 66 AND 76, Kalyan, Thane, 421401. Per the filed land record, the plot is bounded to the north by S NO 66 6 LAND, to the south by S NO 67 5P LAND, to the east by S NO 65 7 LAND and to the west by LAYOUT PLAN NO 1688. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Satyashiv Developers is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Satyashiv Developers

Satyashiv Developers
FlaggedThane
Satyashiv Developers
FlaggedThane

Other RERA-registered projects in Murbad

Arjun Heights
Not filing quarterly progress reports · possession by Dec 2026 · Nanda Arjun Shelke
Madhusudan Retreat Terraces
possession by Dec 2026 · Madhusudan Leisure Homes
SAI Krishna Heights
possession by Dec 2026 · OM SAI Developers
Swami Narendra Residency
possession by Dec 2026 · RAJ Ratneshwari Developers
Techcons Basera
possession by Dec 2026 · Techcons Constructional Engineering Co
Lake Emerald- Phase I
possession by Apr 2027 · N D Enterprises

Other RERA-registered projects in Thane

Shree Siddhivinayak Park Wing A1 AND A2
declared completion Dec 2022 · Satyashiv Developers
Shree Siddhivinayak Residency
declared completion Nov 2020 · Sunil Bhagchand Talreja
Shree Siena
possession by Nov 2032 · Shree Buildcon
Shree Sparsh
possession by Sep 2027 · Omkar Realty
Shree Suvidhinath Complex
declared completion Mar 2019 · Nirav Dhanji Dedhia
Shree Swami Pushpa Phase-1 Shelar Park
declared completion Jun 2023 · Shelar Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026