Mumbai/Project record

MahaRERA · the public record

SHREE VASTU COMPLEX

SAPHALE - WEST · SAI BALAJI HOMES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Nov 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Nov 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000032650

Delivery and registration

When is the project declared for completion?

SHREE VASTU COMPLEX is registered with MahaRERA as P99000032650 and the promoter has declared completion for 30 Nov 2024.

30 Nov 2024

declared completion

22months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000032650
Registered on17 Jan 2022
Promoter-declared completion30 Nov 2024
Current statusCertificate Signed
Against todayabout 22 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHREE VASTU COMPLEX record 12 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 12 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHREE VASTU COMPLEX in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
TYPE B - BUILDING NO 41G+530 Nov 2024
TYPE B - BUILDING NO 51G+530 Nov 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at SAPHALE - WEST, MAKANE, Vasai, Palghar, 401102. Per the filed land record, the plot is bounded to the north by APPROACH ROAD, to the south by VACANT LAND OF GUT NO 348, to the east by BLDG NO 2 AND 3 and to the west by GUT NO 44. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Makane

Excellence Residency 3
possession by Dec 2026 · SAI Excellence Developers
Nayan-Vastu Heritage
Not filing quarterly progress reports · possession by Dec 2026 · Unity Infra
Nayan-Vastu Heritage
possession by Dec 2026 · Unity Infra
Nine Star Prestige Building NO. 1
possession by Dec 2026 · Nine Home Creators
Nine Star Prestige Building NO. 2
possession by Dec 2026 · Nine Home Creators
Ninestar Crown Bldg NO 5 Emerald
possession by Dec 2026 · Nine Homemakers

Other RERA-registered projects in Palghar

Shree Vishnu Garuda
possession by Dec 2027 · Disha HS Developers
Shreeji Apartment
declared completion Aug 2019 · Rishabh Sandeep Tiwari
Shreeji Ashish D- Wing AND CFC
declared completion Mar 2023 · Shreeji Developers
Shreeji Darshan
declared completion Mar 2022 · S.v.realtors
Shreeji Niwas A B C Wing
declared completion Mar 2023 · Shreeji Developers
Shreenath Developers
possession by Dec 2027 · Haresh Pranlal Mehta

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026