168units filed as unsoldInventory · 20 September 2026
31 Mar 2028declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700078231

Delivery and registration

When is the project declared for completion?

SHREEJI DATTAKRUPA is registered with MahaRERA as P51700078231 and the promoter has declared completion for 31 Mar 2028.

31 Mar 2028

declared completion

18months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700078231
Registered on29 Nov 2024
Promoter-declared completion31 Mar 2028
Current statusCertificate Signed
Against today18 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHREEJI DATTAKRUPA record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Construction

How much construction cost has been reported?

In SHREEJI DATTAKRUPA, ₹8.46 Cr of a declared ₹46.29 Cr estimated project cost is reported as incurred, about 18.3%, as at the last certified filing with MahaRERA.

18.3%

₹8.46 Cr

of ₹46.29 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

What the filings record, home by home

Read from MahaRERA on 20 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 14 homes carry one, and 168 of the 199 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
107571 sqftRs 38.97 lakh typical, over Rs 37.99 lakh to Rs 39.47 lakh8 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In SHREEJI DATTAKRUPA, 86 of the 168 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 167 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
BUILDING 51G+7-
BUILDING 41G+5-
BUILDING 31G+1-
BUILDING 21G+1-
BUILDING 11G+1-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at NIKKINAGAR, NEAR AADHARWADI JAIL , Kalyan, Thane, 421301. Per the filed land record, the plot is bounded to the north by SURVEY NO 36 HISSA NO 2 VILLAGE KOLIVALI, to the south by KALYAN VILLAGE BOUNDARY, to the east by KALYAN VILLAGE BOUNDARY and to the west by Survey number 37 Hissa number 2. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kalyan

Bhushan Anand CO OP HSG SOC
possession by Sep 2026 · Dinesh Laxman Sonavane
Ishanvi Ashapura Tower
possession by Sep 2026 · Ishanvi Ashapura Developers
Keshar Aagan Cooperative Housing Society
possession by Sep 2026 · Gagan Homes
Mohan Deep
possession by Sep 2026 · Sunil Purushottam Deshmukh
Parshuram Tower
possession by Sep 2026 · Moreshwar Constructions
Ritz Phase II Commercial Tower D
possession by Sep 2026 · Vikas Harakchand Jain

Major developers building in Kalyan

Other RERA-registered projects in Thane

Shreeji Destiny
declared completion Mar 2026 · Shreeji Ventures Realty Private Limited
Shreeji Destiny NX
possession by Mar 2030 · Kasturi Hotels Private Limited
Shreeji Dios
possession by Dec 2026 · Shreeji Ventures Nirmaan Private Limited
Shreeji Greens
declared completion Jul 2026 · Deep Laxmi Associates
Shreeji Iconic
declared completion Dec 2024 · Shreeji Developers
Shreeji Iconic
possession by Dec 2028 · RAJ Laxmi Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.