SHREEKRUPA HEIGHTS

dronagiri · MADHAV VILLA DEVELOPERS LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000023001

Delivery and registration

When is the project declared for completion?

SHREEKRUPA HEIGHTS is registered with MahaRERA as P52000023001 and the promoter has declared completion for 31 Dec 2026.

31 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000023001
Registered on11 Nov 2019
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHREEKRUPA HEIGHTS record 27 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Madhav Villa Developers is the promoter of record on 61 projects registered with MahaRERA, 9 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

61projects

registered with MahaRERA

9flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHREEKRUPA HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
SHREEKRUPA HEIGHTS1G+15-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2026The Project could be completed on the due date i.e., 30th December 2024, but due to unforeseen challenges encountered during the execution of the project, we are unable to meet the

Location, Land & Connectivity

Located at dronagiri, sector-54, Thane, Thane, 400702. Per the filed land record, the plot is bounded to the north by 22 mtrs wide road, to the south by plot no 49 and 50 and 51, to the east by plot no 40 and to the west by plot no 42. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dronagiri

Shree Laxmi Coop Housing Society
possession by Sep 2026 · Mohit Mayuresh Gangal
Siddhivinayak Apartments
possession by Nov 2026 · Baldev Diwan Singh
Phoenix
possession by Dec 2026 · Adarsh Enterprises
Aaradhy Heights
possession by Dec 2026 · Lambodar Infra
Avantika Aura
possession by Dec 2026 · Riddhi Developer
Bombay Chalet
possession by Dec 2026 · Bombay Shiva Plus LLP

Other RERA-registered projects in Raigarh

Shreekrupa Heramb
possession by Dec 2029 · Shree Krupa Investment
Shreenath Darshan CHS
declared completion Jun 2025 · Nexus Home LLP
Shreeniwas Enterprises
declared completion Jul 2023 · Shreeniwas Enterprises
Shreepad Developers
declared completion Jan 2025 · Mangesh Ramling Tatode
Shreepati 171
possession by Dec 2026 · Siddhivinayak Homes
Shreepati Amara
possession by Jun 2027 · M/s Rudra Lifespaces

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.