MahaRERA Property Intelligence · Mumbai City

SHREEPATI BAYVIEW

P51900010019 · promoter Shreepati Build Infra

Certificate SignedDue 30 Dec 2026

Delivery & Registration

MahaRERA registrationP51900010019
Registered on23 Aug 2017
Promoter-declared completion30 Dec 2026
Current statusCertificate Signed
Against today5 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shreepati Build Infra is the promoter of record on 43 projects, of which 3 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Sales & Inventory

Of 399 homes filed with MahaRERA, 0 are sold/booked and 399 remain available (~0% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23 and 399 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
GIRGAON EKTA SOCIETY1G+23-30 Jun 2026
WING B1G+1915530 Dec 2026
WING C1G+2323730 Dec 2026
WING D1G+22730 Jun 2026
WING E1G+23-30 Jun 2026

Unit mix on the filing: 399 residential.

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000005663619/10/2018PROZONE DEVELOPERS & REALTORS PRIVATE LIMITED vs Shreepati Build Infra Investment Private Limitedorder passed

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High CourtWP/209/20152015Preadmission
High Court9782018Pre Admission

Location, Land & Connectivity

Located at Ward ABCD, Mumbai City, 400004. Per the filed land record, the plot is bounded to the north by JAGANNATH SHANKAR SETH ROAD, to the south by CS NO 3, to the east by CS NO 1 and to the west by CS NO 1-61. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Nariman Point / Fort4 km
Lower Parel / Worli business district5 km
Bandra Kurla Complex (BKC)13 km
Chhatrapati Shivaji Int'l Airport15 km
Andheri MIDC / SEEPZ20 km
Powai / Hiranandani business park20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shreepati Build Infra Investment Limited is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Shreepati Build Infra Investment Limited project & its RERA track record →

Other flagged projects by Shreepati Build Infra Investment Limited

Shreepati Build Infra Investment Limited
FlaggedMumbai City
Shreepati Build Infra Investment Limited
FlaggedMumbai City

Other RERA-registered projects in Girgaon

Krishvi Heights
possession by Aug 2026 · M/s Shagun Associates
Sugee Renaissance
possession by Sep 2026 · Sugee Two Developers LLP
M4 Aarambh
possession by Dec 2026 · M4 Realty LLP
Aaditya Residences
possession by Dec 2026 · M/s. A.k. Developers
THE Platinum
possession by Dec 2026 · Rubberwala Housing & Infrastructure
Anantaya Apartments
possession by Dec 2026 · Sanskriti Developers

Major developers building in Girgaon

Other RERA-registered projects in Mumbai City

Shreepati Castle
declared completion Dec 2024 · Shreepati Castle
Shreepati Coronet
possession by Dec 2026 · Shreepati Build Infra Investment Limited
Shreepati Jewels
possession by Dec 2032 · Shreepati Jewels
Shreepati Skies
possession by Dec 2026 · Shreepati Skies
Shreeya
declared completion Sep 2022 · Vilas Ashok Chaudhari
Shri Abhinandan
declared completion Dec 2025 · Ratnaraj Builders AND Developers LLP

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026