Mumbai/Project record

MahaRERA · the public record

SHREEPATI BAYVIEW

Mumbai City · SHREEPATI BUILD INFRA INVESTMENT LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

399units filed as unsoldInventory · 12 September 2026
30 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
399registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900010019

Delivery and registration

When is the project declared for completion?

SHREEPATI BAYVIEW is registered with MahaRERA as P51900010019 and the promoter has declared completion for 30 Dec 2026.

30 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900010019
Registered on23 Aug 2017
Promoter-declared completion30 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHREEPATI BAYVIEW record 36 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Deregistered — MahaRERA has deregistered this project — it is off the register.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Shreepati Build Infra is the promoter of record on 44 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

44projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In SHREEPATI BAYVIEW, 0 of 399 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 399 remain available.

0%sold

0 of 399 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHREEPATI BAYVIEW in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 September 2026

What the filings record, home by home

Read from MahaRERA on 12 September 2026

No home in SHREEPATI BAYVIEW carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 397 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 30,938 a sq ft typical, over Rs 29,465 to Rs 33,885.

A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.

The Reckoner Record lists all 397 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.

See all 397 filed valuations — ₹999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23 and 399 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
GIRGAON EKTA SOCIETY1G+23-30 Jun 2026
WING B1G+1915530 Dec 2026
WING C1G+2323730 Dec 2026
WING D1G+22730 Jun 2026
WING E1G+23-30 Jun 2026

Unit mix on the filing: 399 residential.

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for SHREEPATI BAYVIEW, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000005663619/10/2018PROZONE DEVELOPERS & REALTORS PRIVATE LIMITED vs Shreepati Build Infra Investment Private Limitedorder passed

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High CourtWP/209/20152015Preadmission
High Court9782018Pre Admission

Location, Land & Connectivity

Located at Ward ABCD, Mumbai City, 400004. Per the filed land record, the plot is bounded to the north by JAGANNATH SHANKAR SETH ROAD, to the south by CS NO 3, to the east by CS NO 1 and to the west by CS NO 1-61. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Nariman Point / Fort4 km
Lower Parel / Worli business district5 km
Bandra Kurla Complex (BKC)13 km
Chhatrapati Shivaji Int'l Airport15 km
Andheri MIDC / SEEPZ20 km
Powai / Hiranandani business park20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shreepati Build Infra Investment Limited is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Shreepati Build Infra Investment Limited project & its RERA track record →

Other flagged projects by Shreepati Build Infra Investment Limited

Shreepati Build Infra Investment Limited
FlaggedMumbai City

Other RERA-registered projects in Girgaum

Aaditya Residences
possession by Dec 2026 · M/s. A.k. Developers
NEO Amity
possession by Dec 2026 · Naresh Kesarimal Mehta
Onyx
possession by Dec 2026 · Naminath Erector And Developers LLP
Promesa Castor
possession by Dec 2026 · Darshan Group
Raajdeep Arcade
possession by Dec 2026 · Raajdeep Builders AND Developers
Sach Vintage
possession by Dec 2026 · Ushadevi Vijaykumar Chandan

Other RERA-registered projects in Mumbai City

Shreepati Castle
declared completion Dec 2024 · Shreepati Castle
Shreepati Coronet
possession by Dec 2026 · Shreepati Build Infra Investment Limited
Shreepati Skies
possession by Dec 2026 · Shreepati Skies
Shreeya
declared completion Sep 2022 · Vilas Ashok Chaudhari
Shri Abhinandan
declared completion Dec 2025 · Ratnaraj Builders AND Developers LLP
Shri Gana Siddhivinayak SRA CHS Ltd
declared completion Mar 2022 · Gharandaj Builders

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026