Mumbai/Project record

MahaRERA · the public record

Shri Parrsssva Eleganza

Ghatkopker West · Sanghvi Constructions

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Mar 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Mar 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800009496

Delivery and registration

When is the project declared for completion?

Shri Parrsssva Eleganza is registered with MahaRERA as P51800009496 and the promoter has declared completion for 30 Mar 2021.

30 Mar 2021

declared completion

66months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800009496
Registered on22 Aug 2017
Promoter-declared completion30 Mar 2021
Current statusCertificate Signed
Against todayabout 66 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Shri Parrsssva Eleganza record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sanghvi Constructions is the promoter of record on 48 projects registered with MahaRERA, 8 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

48projects

registered with MahaRERA

8flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Shri Parrsssva Eleganza in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
Shri Parrsssva Eleganza1G+11-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Sep 2020We are proposing amendment in plan for 10th floor, hence for the purpose of obtaining approval and to commence work we require further time extension.
30 Sep 202030 Sep 2020The project is having further proposed FSI to be consumed, so the firm intend to build further units in the project. Due to final formalities with BMC, we need further extension of

Location, Land & Connectivity

Located at Ghatkopker West, Jivdaya Lane, Ward ABCD, Mumbai City, 400086. Per the filed land record, the plot is bounded to the north by Khoti land, to the south by Jivdaya Road, to the east by Land Belongs to Pragji Naranji and to the west by Another land belong to Pragji Naranji. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Powai / Hiranandani business park3 km
Chhatrapati Shivaji Int'l Airport4 km
Bandra Kurla Complex (BKC)5 km
Andheri MIDC / SEEPZ6 km
Lower Parel / Worli business district13 km
Nariman Point / Fort20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sanghvi Constructions is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Sanghvi Constructions

Sanghvi Constructions
FlaggedMumbai Suburban

Other RERA-registered projects in Ghatkopar West

O AND S Royale
possession by Dec 2026 · Suchita Orange Project Royale
Sarvonnati CHS LTD
Deregistered by MahaRERA · possession by Dec 2026 · JAI Enterprises
Vighneshwar Cooperative Housing Society Limited
possession by Dec 2026 · Vighneshwar Coop Housing Society Limited
Arihant Heights
possession by Dec 2026 · Arihant Infrastructure Company
Avani Signature
possession by Dec 2026 · Avani Buildcon
Sanghvi Parsssva Jivdaya
possession by Dec 2026 · Sanghvi Constructions

Other RERA-registered projects in Mumbai Suburban

Shri SAI Krupa
possession by Jan 2027 · Arham Realty
Shri Shankarpuri
possession by Feb 2030 · Mr. Suresh Prabhushankar Sharma, Mr. Raj
Shri Siddhivinayak BY DEM
declared completion Jun 2026 · DEM Realty LLP
Shri Upendra Chsl
possession by Dec 2026 · Harshal Enterprises
Shriji Heritage
declared completion Dec 2025 · Shriji Apartments CO-Operative Housing S
Shrikant Chembers II
declared completion Mar 2023 · Shrikant Studios Pvt. Ltd.

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026