MahaRERA Property Intelligence · Thane

SIDDHICITY

P51700001597 · promoter Siddhitech Homes Private

Certificate SignedDue 30 Jun 2019

Delivery & Registration

MahaRERA registrationP51700001597
Registered on29 Jul 2017
Promoter-declared completion30 Jun 2019
Current statusCertificate Signed
Against todayabout 85 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Siddhitech Homes Private is the promoter of record on 3 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
21G+8-
31G+8-
41G+8-
51G+8-
61G+8-
71G+8-
81G+8-
91G+8-
101G+8-
111G+8-
121G+8-

Complaints & Orders

15 complaints are on the MahaRERA record for this project, with orders passed in 15. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000000111611/10/2017VARSHA.D.PARIANI vs HEMANT AGARWALorder passed
CC00600000000169711/11/2017Sujay Parkar vs Siddhitech Homes Pvt Ltdorder passed
CC00600000002336816/02/2018KARANVEER SINGH SACHDEV vs Siddhitech Homes Private Limitedorder passed
CC00600000005804014/02/2019Mohammad Shaban Shaikh vs Siddhitech Homes Private Limitedorder passed
CC00600000005803913/02/2019Abdul Kader Batliwala vs Siddhitech Homes Private Limitedorder passed
CC00600000018200728/12/2019HARIHARAN PARAMESHWARAN vs Hemant Agrawalorder passed
CC00600000012094321/10/2019Sudha Pillai vs M/s. Siddhitech Homes Pvt. Ltd.order passed
CC00600000016131421/10/2019KR Pillai vs M/s. Siddhitech Homes Pvt. Ltd.order passed
CC00600000016130820/10/2019Dhanwant Singh Bala vs M/s. Siddhitech Homes Pvt. Ltd.order passed
CC00600000016130920/10/2019Kamaljit Kaur Bala vs M/s. Siddhitech Homes Private Limitedorder passed
CC00600000016131031/10/2019LATA PATANE vs siddhitech homes pvt ltdorder passed
CC00600000017157320/11/2019sudama eppili vs Hemant Agarwalorder passed
CC00600000017180828/12/2019KRISHNAN PARAMESWARAN vs HEMANT AGRAWALorder passed
CC00600000018204622/01/2020Avtar Singh Sachdev vs Siddhitech Homes Private Limitedorder passed
CC00600000020998622/03/2022Suadam Eppili vs M/s SIddhitechHomes Pvt Ltdorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 201930 Jun 2019Applied for Part Occupation Certificate for 6 buildings(Bldg No- 7 to 12) Delay in competition of work Bldg no-6 Occupation Certificate application for Bldg no- 2 ,3,4 and 5 wi

Location, Land & Connectivity

Located at Ward GSouth, Mumbai City, 421503. Per the filed land record, the plot is bounded to the north by Bhaga Bapu Bhagat and Atmaram Hasu Bhagatto, to the south by Laagun Hemlata Bachu Bhai Hinguto , to the east by Sita Bai Vishnu Jamdare and to the west by Laxmi Bai Maruti Jamdai. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~36 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park36 km
Andheri MIDC / SEEPZ40 km
Chhatrapati Shivaji Int'l Airport40 km
Bandra Kurla Complex (BKC)41 km
Lower Parel / Worli business district47 km
Nariman Point / Fort50 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Siddhitech Homes Private Limited is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Siddhitech Homes Private Limited

Siddhitech Homes Private Limited
FlaggedThane

Other RERA-registered projects in Badlapur

Ekdant Pooja Chsl
possession by Jul 2026 · Landmark Infra
OM Shiv Darshan
possession by Jul 2026 · Vinayak Enterprises Developers
RAJ Silverstone Phase-2
possession by Jul 2026 · Skyspace Builtek
Sairaj Avenue Wing B
possession by Jul 2026 · Virendra Atmaram Salunkhe
Satyam Sheela Wing F
possession by Jul 2026 · Shreeji Developers
Shreeji Greens
possession by Jul 2026 · Deep Laxmi Associates

Major developers building in Badlapur

Other RERA-registered projects in Thane

Siddhicity Phase-V
declared completion Dec 2021 · Siddhitech Homes Private Limited
Siddhivinayak
possession by Dec 2026 · Shreeashtavinayak Enterprises
Siddhivinayak Apartment
declared completion Mar 2026 · GLR Construction & Infraprojects
Siddhivinayak Arcade
possession by Dec 2026 · Siddhivinayak Builders & Developers
Siddhivinayak Aura Building - 1
possession by May 2029 · Varadvinayak Developers
Siddhivinayak Enclave
possession by Dec 2028 · Siddhi Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026