Mumbai/Project record

MahaRERA · the public record

Siddhivinayak Complex

Palghar · ARYANS ASSOCIATES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000013141

Delivery and registration

When is the project declared for completion?

Siddhivinayak Complex is registered with MahaRERA as P99000013141 and the promoter has declared completion for 31 Dec 2024.

31 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000013141
Registered on14 Sep 2017
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Siddhivinayak Complex record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 30 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Aryans Associates is the promoter of record on 6 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

6projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Siddhivinayak Complex in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
SIDDHIVINAYAK COMPLEX BUILDING 2 WING A1G+7-
SIDDHIVINAYAK COMPLEX BUILDING 2 WING B1G+9-
SIDDHIVINAYAK COMPLEX BUILDING 2 WING C1G+9-
SIDDHIVINAYAK COMPLEX BUILDING 2 WING D1G+9-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered31 Mar 2022DUE TO UNAVOIDABLE REASON PROJECT COULD NOT COMPLETED ON OR BEFORE THE DUE DATE
31 Mar 202231 Mar 2022MANY FINANCIAL INSTITUTION LIKE DHFL, INDIABULLS ETC HAVE PUT HOLD ON DISBURSEMENT WHICH ADVERSELY AFFECTED THE CONSTRUCTION WORK AND BECAUSE OF WHICH CONSTRUCTION CAN NOT BE COMPL
31 Mar 202231 Dec 2024THE PROJECT WAS DELAYED DUE TO PANDEMIC

Location, Land & Connectivity

Located at Vasai, Palghar, 401501. Per the filed land record, the plot is bounded to the north by GUT NO 138, to the south by GUT NO 136, to the east by GUT NO 139 and to the west by GUT NO 283. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~69 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ69 km
Powai / Hiranandani business park71 km
Chhatrapati Shivaji Int'l Airport74 km
Bandra Kurla Complex (BKC)76 km
Lower Parel / Worli business district84 km
Nariman Point / Fort92 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Boisar

Classic Apartment
possession by Sep 2026 · I.k.group
Divyajal
possession by Sep 2026 · Divyaraj Properties LLP
Kinjal Complex II
possession by Sep 2026 · Kinjal Enterprises
Queens Villa - 2
possession by Sep 2026 · Super Realty
Marathe Complex
possession by Dec 2026 · Gprs Realty
Rajhans United Regency III
possession by Dec 2026 · Rajhans Homes

Other RERA-registered projects in Palghar

Siddhivinayak Complex
possession by Dec 2026 · Sugandhi Realtors
Siddhivinayak Crown
possession by Dec 2028 · Siddhivinayak Delevopers
Siddhivinayak Enclave
possession by Dec 2030 · Navratna Developers
Siddhivinayak Heights
declared completion Jul 2025 · Shree Siddhivinayak Realtors
Sierra
possession by Dec 2030 · Shrushti Developers
Signature Galaxy Apartment
declared completion Dec 2025 · Mohd Sajid Ashfaqueahd Khan

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026