SIGNATURE-I

P51800004538 · promoter Chaubey Realties Private

Certificate SignedDue 30 Jan 2023

Delivery & Registration

MahaRERA registrationP51800004538
Registered on09 Aug 2017
Promoter-declared completion30 Jan 2023
Current statusCertificate Signed
Against todayabout 42 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Chaubey Realties Private is the promoter of record on 126 projects, of which 12 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+27.

BuildingWingsFloorsDeclared completion
SIGNATURE-11G+27-

Complaints & Orders

2 complaints are on the MahaRERA record for this project, with orders passed in 2. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000000106907/10/2017NEHA VIKRANT SHINDE vs Chaubey realities pvt ltdorder passed
CC00600000005669424/10/2018Urmil Mehta vs Chaubey Realities Pvt Ltd.order passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jan 202330 Jan 2022due to company going through the insolvency process the project will not be able to get completed upto 2021 however the project shall be completed by december 2022. request you to

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 400066. Per the filed land record, the plot is bounded to the north by KARTIKE BUILDING, to the south by PROPOSED SIGNATURE-II, to the east by SN DUBE ROAD and to the west by GOPI KRISHNA NAGAR. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ11 km
Powai / Hiranandani business park13 km
Chhatrapati Shivaji Int'l Airport16 km
Bandra Kurla Complex (BKC)18 km
Lower Parel / Worli business district26 km
Nariman Point / Fort34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Borivali East

Rushabh Apartment
possession by Jul 2026 · R R Builders
Rashmi Manorath
possession by Aug 2026 · Modi's Navnirman Limited
Proposed Redevelopment OF Prakashkunj Chsl
possession by Sep 2026 · Yash Realtors & Developers
Chandratej CHS LTD
possession by Oct 2026 · Elesh Ravjibhai Rathod
Eknath Gruh
possession by Oct 2026 · Vastav Developers PVT LTD
NEW Avanti Chsl
possession by Oct 2026 · Balaji Enterprises

Major developers building in Borivali East

Other RERA-registered projects in Mumbai Suburban

Signature Residences BY C.k.v
possession by Dec 2031 · Neelam Dream Lands LLP
Signet
possession by Oct 2026 · DG Builders
Signia
possession by Mar 2030 · Headway Believe Realty LLP
Signia High, Magathane, Western Express Highway, Borivali East
declared completion Feb 2021 · Sunteck Realty Limited
Signia Pearl Phase 2, Plot R.1.1, G Block, Bandra Kurla Complex, Bandra East
declared completion Dec 2021 · Starlight Systems LLP
Silicon Avenue
possession by Dec 2027 · Silicon Lifespaces LLP

What to verify (NCLT insolvency)

  1. Check the IRP/Resolution Professional's name on the NCLT cause list and contact them for a project status update.
  2. Verify whether a Resolution Plan has been approved — the IRP's report is filed with NCLT and is public.
  3. Look for a homebuyers' association for this project — allottee groups have legal standing in insolvency proceedings.
  4. Consult a RERA or IBC advocate about your rights under Section 7 IBC or Section 18 RERA for possession or refund.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026