Mumbai/Project record

MahaRERA · the public record

SIGNATURE RESIDENCY BUILDING NO. 1

Palghar · SAI REALTY

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000006949

Delivery and registration

When is the project declared for completion?

SIGNATURE RESIDENCY BUILDING NO. 1 is registered with MahaRERA as P99000006949 and the promoter has declared completion for 31 Mar 2023.

31 Mar 2023

declared completion

42months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000006949
Registered on16 Aug 2017
Promoter-declared completion31 Mar 2023
Current statusCertificate Signed
Against todayabout 42 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SIGNATURE RESIDENCY BUILDING NO. 1 record 23 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 23 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SIGNATURE RESIDENCY BUILDING NO. 1 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
BULDING NO 11G+531 Jul 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2021Delay occurred due to the pandemic situation causing slowdown in work speed as well as sales. But now project is on the verge of completion & will be definitely completed before th
31 Dec 202131 Mar 2023Delay occurred due to the pandemic situation causing slowdown in work speed as well as sales. But now project is on the verge of completion & will be definitely completed before th

Location, Land & Connectivity

Located at Palghar, Palghar, 401402. Per the filed land record, the plot is bounded to the north by HARANWADI ROAD, to the south by PALGHAR MAHIM ROAD, to the east by S N 930 and to the west by S N 1023-A AND 25. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~60 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ60 km
Powai / Hiranandani business park63 km
Chhatrapati Shivaji Int'l Airport64 km
Bandra Kurla Complex (BKC)67 km
Lower Parel / Worli business district74 km
Nariman Point / Fort82 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

SAI Realty is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by SAI Realty

Other RERA-registered projects in Palghar

Sanmukh Sunshine
Not filing quarterly progress reports · possession by Oct 2026 · Sanmukh Realty LLP
Bafna Luxuria
possession by Dec 2026 · Shrushti Developers
Krishna Solitaire - 1
possession by Dec 2026 · Inspiration SG Infracon LLP
Krishna Solitaire - 2
possession by Dec 2026 · Inspiration SG Infracon LLP
Shakti Industrial Estate
Not filing quarterly progress reports · possession by Dec 2026 · Shakti Krupa Developers
Star Signature City-Star Emerald
possession by Dec 2026 · Star Builders & Developers

Other RERA-registered projects in Palghar

Signatureclassic
declared completion Dec 2025 · Bharatbhai Devjibhai Bhasotiya
Silver Green
possession by Dec 2026 · Acres Developers
Simandhar Indusrial Estate
declared completion Oct 2024 · Space Infratech
Sitamai Complex
declared completion Dec 2021 · R J P Developers
Sitaram Heights
declared completion Jun 2025 · M/s. Om Sai Ram Infra
SK Heights
possession by Dec 2030 · S.S Buildcare Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026