Mumbai/Project record

MahaRERA · the public record

SILVER CASTLE

PANVEL · MEGHNA BUILDERS AND DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000023846

Delivery and registration

When is the project declared for completion?

SILVER CASTLE is registered with MahaRERA as P52000023846 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000023846
Registered on07 Jan 2020
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SILVER CASTLE record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 16 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Meghna Builders is the promoter of record on 12 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

12projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SILVER CASTLE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
SILVER CASTLE1G+1431 Dec 2021

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for SILVER CASTLE, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000039630013/07/2023Aruna Vilas Ambardekar vs Prem Rathod and Baliram Rathodorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2023Due to COVID 19 We could not complete our project. Now we Just need one year of extension to complete our project.

Location, Land & Connectivity

Located at PANVEL, URAN, Thane, Thane, 400702. Per the filed land record, the plot is bounded to the north by PLOT NO 33, to the south by PLOT NO 35, to the east by 15MTR WIDE ROAD and to the west by PLOT NO 40 AND 41. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dronagiri

Shree Laxmi Coop Housing Society
possession by Sep 2026 · Mohit Mayuresh Gangal
Siddhivinayak Apartments
possession by Nov 2026 · Baldev Diwan Singh
Phoenix
possession by Dec 2026 · Adarsh Enterprises
Aaradhy Heights
possession by Dec 2026 · Lambodar Infra
Avantika Aura
possession by Dec 2026 · Riddhi Developer
Bombay Chalet
possession by Dec 2026 · Bombay Shiva Plus LLP

Other RERA-registered projects in Raigarh

Silver Crest
declared completion Dec 2023 · Hare Krishna Enterprises
Silver Fern
declared completion Jun 2026 · Micron Aspire Developers
Silver Icon
declared completion Dec 2022 · Silver Properties
Silver Springs
declared completion Dec 2024 · Arss Ravechi Ratna Developers
Silvra ONE
possession by Dec 2027 · Bonzer Infra Private Limited
Sirvi Complex
declared completion Dec 2022 · Aaiji Group

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026