Mumbai/Project record

MahaRERA · the public record

SILVER LINE PHASE - 1

VASUNDRI · HOME CONSULTANCY

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

716units filed as unsoldInventory · 18 September 2026
01 Mar 2031declared completionMahaRERA registration · read 12 Jul 2026
716registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

01 Mar 2031

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700027713

Delivery and registration

When is the project declared for completion?

SILVER LINE PHASE - 1 is registered with MahaRERA as P51700027713 and the promoter has declared completion for 01 Mar 2031.

01 Mar 2031

declared completion

54months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700027713
Registered on03 Jan 2021
Promoter-declared completion01 Mar 2031
Current statusCertificate Signed
Against today54 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SILVER LINE PHASE - 1 record 17 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 17 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Home Consultancy is the promoter of record on 12 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

12projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In SILVER LINE PHASE - 1, ₹81.72 Lakh of a declared ₹8.23 Cr estimated project cost is reported as incurred, about 9.9%, as at the last certified filing with MahaRERA.

9.9%

₹81.72 Lakh

of ₹8.23 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In SILVER LINE PHASE - 1, 0 of 716 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 716 remain available.

0%sold

0 of 716 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SILVER LINE PHASE - 1 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 September 2026

What the filings record, home by home

Read from MahaRERA on 18 September 2026

No home in SILVER LINE PHASE - 1 carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 716 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 2,708 a sq ft typical, over Rs 2,670 to Rs 3,781.

A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.

The Reckoner Record lists all 716 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.

See all 716 filed valuations — ₹999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 716 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
BUILDING NO - 1 (Wing-A+B+C)1G+79901 Sep 2030
BUILDING NO - 2 (Wing-A+B+C+D)1G+715901 Sep 2030
BUILDING NO - 3 (Wing-A+B)1G+712301 Sep 2030
BUILDING NO - 4 (Wing-A+B)1G+76101 Sep 2030
BUILDING NO - 5 (Wing-A+B+C)1G+79001 Sep 2030
BUILDING NO - 6 (Wing-A+B)1G+79401 Sep 2030
BUILDING NO - 7 (Wing-A+B+C)1G+790-

Unit mix on the filing: 683 residential and 33 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at VASUNDRI, VASUNDRI ROAD, Mumbai City, Mumbai City, 421605. Per the filed land record, the plot is bounded to the north by PLOT, to the south by ROAD, to the east by PLOT and to the west by BAILGADI ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~23 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park23 km
Andheri MIDC / SEEPZ26 km
Chhatrapati Shivaji Int'l Airport28 km
Bandra Kurla Complex (BKC)29 km
Lower Parel / Worli business district36 km
Nariman Point / Fort42 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Titwala

Ganpati Heights
possession by Sep 2026 · Manoj Prabhakar Patil
Indrayani
possession by Oct 2026 · Naresh Yashwant Patil
Mantra
possession by Nov 2026 · Vaidikh Nirmaan LLP
Rusttagi Aarambha 2.0
possession by Nov 2026 · Rustagi Estates Private Limited
Ganpati Prasanna
possession by Dec 2026 · Vijay Prabhakar Patil
Hillcrest Appartments
possession by Dec 2026 · Aasanghar Construction

Other RERA-registered projects in Thane

Silver OAK Apartment
declared completion Mar 2025 · Ashokkumar Topanlal Dewani
Silver Park Residency Orchid
declared completion Dec 2022 · Suyash Enterprises
Silver Plaza
possession by Mar 2029 · Shree Shivam Developers
Silver Spring
declared completion Dec 2025 · M/s. Shri Venkatesh Ramdev Homes
Silver Square
possession by Dec 2026 · Ramdev Venkatesh Housing
Silver Wood
possession by May 2028 · Mangala Construction

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026