MahaRERA Property Intelligence · Raigarh

SIYA 24K

P52000028244 · PANCHAYAT SAMITI MAHAD · promoter Nilesh Satish Mehta

Certificate SignedDue 30 Jun 2025

Delivery & Registration

MahaRERA registrationP52000028244
Registered on18 Feb 2021
Promoter-declared completion30 Jun 2025
Current statusCertificate Signed
Against todayabout 13 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Nilesh Satish Mehta is the promoter of record on 73 projects, of which 11 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
SIYA 24K1G+531 Dec 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at PANCHAYAT SAMITI MAHAD, KAKARTALE, Mahad, Raigarh, 402301. Per the filed land record, the plot is bounded to the north by MUMBAI GOA HIGHWAY, to the south by MAHAD PANCHAYAT SAMITI, to the east by REMAINING PART OF S NO 79 and to the west by REMAINING PART OF S NO 80. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~120 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort113 km
Lower Parel / Worli business district120 km
Bandra Kurla Complex (BKC)124 km
Chhatrapati Shivaji Int'l Airport127 km
Powai / Hiranandani business park128 km
Andheri MIDC / SEEPZ130 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Nilesh Satish Mehta is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Nilesh Satish Mehta

Nilesh Satish Mehta
FlaggedRaigarh

Other RERA-registered projects in Mahad

Chandrabhaga Residency
possession by Dec 2026 · Rajesh Namdev Pawale
Herai Complex - B Wing, Hajwane Complex- C Wing
possession by Dec 2026 · Akhtar Ahmed Lambade
Raigad City
possession by Dec 2026 · Dhanalaxmi Realtors
SAI Nandanvan
possession by Dec 2026 · Stuti Developers
Vedika Hills
Not filing quarterly progress reports · possession by Dec 2026 · Rajendra Mehetar Krishana
Aditi Apartment
possession by Dec 2026 · Aijaz Ismail Darekhan

Other RERA-registered projects in Raigarh

SKY Canary
declared completion Mar 2019 · Aadhar Infra Project
SKY Copper
declared completion Aug 2023 · Shrey Infra Project
SKY Corral
declared completion Mar 2019 · SKY City Developers
SKY Creeva
declared completion Jul 2022 · Shrey Infra
SKY Empire
possession by Jul 2029 · Girija Realtors LLP
SKY Exotica
possession by Dec 2026 · SKY City Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026