30 Jun 2029declared completionMahaRERA registration · read 02 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 02 Jul 2026

The record · free to read

Registration read 02 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2029

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 02 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PM1180002502849

Delivery and registration

When is the project declared for completion?

SOHAM HORIZON is registered with MahaRERA as PM1180002502849 and the promoter has declared completion for 30 Jun 2029.

30 Jun 2029

declared completion

33months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 02 Jul 2026

MahaRERA registrationPM1180002502849
Registered on16 Mar 2026
Promoter-declared completion30 Jun 2029
Current statusCertificate Signed
Against today33 months to the declared date

Construction

How much construction cost has been reported?

In SOHAM HORIZON, ₹0 of a declared ₹36.50 Cr estimated project cost is reported as incurred, about 0.0%, as at the last certified filing with MahaRERA.

0.0%

₹0

of ₹36.50 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 02 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SOHAM HORIZON in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 02 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+0.

BuildingWingsFloorsDeclared completion
MALVANI SUYOG CO-OP.HOS.SOC LTD2G+0-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for SOHAM HORIZON, with orders passed in 0 of them.

1complaint

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 02 Jul 2026

Complaint no.FiledPartiesStatus
CC1260232520/04/2026Firoz Faruq Shaikh vs SAISOHAM INFRA LLPpending / no order on file

Location, Land & Connectivity

Located at Malad, Malwani Suyog CHSL, Borivali, Mumbai Suburban, 400095. Per the filed land record, the plot is bounded to the north by Road North side, to the south by Plot No 95 Vedashree CHS, to the east by Ashiyana CHS Building and to the west by Plot 97 Utkarsh Chs. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ8 km
Powai / Hiranandani business park12 km
Chhatrapati Shivaji Int'l Airport12 km
Bandra Kurla Complex (BKC)14 km
Lower Parel / Worli business district21 km
Nariman Point / Fort29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Malad West

95 West Composite
possession by Dec 2026 · Stans Buildtech Realty
BAY VUE
possession by Dec 2026 · H AND Y Realities Private Limited
Galaxy Heights Tower 1
possession by Dec 2026 · Maharashtra Police Cooperative Housing F
Lotus
possession by Dec 2026 · Rajeshwar Land Developers Private Limite
Royal Lagoon E Wing
possession by Dec 2026 · Rikki Ronie Developers
Royal Lagoon F Wing
possession by Dec 2026 · Rikki Ronie Developers

Other RERA-registered projects in Mumbai Suburban

Soham Regency
declared completion Dec 2017 · Laxmikant Ramchandra Sawant
Soham Villa
declared completion Dec 2025 · Mahesh Daryanumal Thakkar
Solaris 14th Floor
declared completion Jun 2026 · Hubtown Limited
Solaris Bhagyashree
declared completion Dec 2019 · Solaris Developers Private Limited
Solaris Platinum
declared completion Dec 2020 · Solaris Developers Private Limited
Solaris Titanium Towers
declared completion Dec 2019 · Solaris Developers Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026