SUDAMA REGENCY BUILDING NO 2,3,4

Khardi Pada · SHREE SIDDHIVINAYAK ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

153units filed as unsoldInventory · 13 September 2026
29 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

29 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700001217

Delivery and registration

When is the project declared for completion?

SUDAMA REGENCY BUILDING NO 2,3,4 is registered with MahaRERA as P51700001217 and the promoter has declared completion for 29 Dec 2024.

29 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700001217
Registered on27 Jul 2017
Promoter-declared completion29 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SUDAMA REGENCY BUILDING NO 2,3,4 record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 30 quarterly progress reports on record since registration, with no current default.

What the filings record, home by home

Read from MahaRERA on 13 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 54 homes carry one, and 153 of the 346 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
1001350 sqftRs 20.78 lakh typical, over Rs 15.35 lakh to Rs 27.40 lakh13 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In SUDAMA REGENCY BUILDING NO 2,3,4, 123 of the 153 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 152 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23.

BuildingWingsFloorsDeclared completion
SUDAMA REGENCY BUILDING NO 21G+2331 Dec 2022
SUDAMA REGENCY BUILDING NO 31G+2331 Dec 2022
SUDAMA REGENCY BUILDING NO 41G+2331 Dec 2022

Legal and disputes

What disputes are disclosed?

6 complaints are on the MahaRERA record for SUDAMA REGENCY BUILDING NO 2,3,4, with orders passed in 6 of them.

6complaints

6with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000005471801/06/2018Bhavanj Kanji Shah vs Shree Siddhivinayak Enterprisesorder passed
CC00600000005472101/06/2018Jigna A. Shah vs Shree Siddhivinayak Enterprisesorder passed
CC1250074805/03/2025Ashwin Bhavanji Shah vs SHREE SIDDHIVINAYAK ENTERPRISESorder passed
CC1250074505/03/2025Jigna Ashwin Shah vs SHREE SIDDHIVINAYAK ENTERPRISESorder passed
CC1250075005/03/2025Maitri Ashwin Shah vs SHREE SIDDHIVINAYAK ENTERPRISESorder passed
CC1250094218/03/2025Jigna Ashwin Shah vs SHREE SIDDHIVINAYAK ENTERPRISESorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered29 Dec 2024The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted t

Location, Land & Connectivity

Located at Khardi Pada, Diva Shill Road, Thane, Thane, 400612. Per the filed land record, the plot is bounded to the north by 60 MTR DP ROAD, to the south by 7 AND HALF MTR INTERNAL ROAD, to the east by SURVEY NO 165 and to the west by 30 MTR DP ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~16 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park16 km
Andheri MIDC / SEEPZ19 km
Chhatrapati Shivaji Int'l Airport21 km
Bandra Kurla Complex (BKC)22 km
Lower Parel / Worli business district30 km
Nariman Point / Fort36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shree Siddhivinayak Enterprises is the promoter on 5 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Shree Siddhivinayak Enterprises

Shree Siddhivinayak Enterprises
FlaggedRaigarh
Shree Siddhivinayak Enterprises
FlaggedThane

Other RERA-registered projects in Mumbra

Celosia Avenue
possession by Sep 2026 · Pratima Construction
Quality Annex
possession by Sep 2026 · Quality Annex
YES Central Galleria
possession by Oct 2026 · Noble Enterprises
YES Central Galleria 1
possession by Oct 2026 · YES Enterprises
Sagar Enclave
possession by Dec 2026 · Kanchan Builders & Developers
Grace Square Type D3
possession by Dec 2026 · Shree Sumatinath Enterprises LLP

Major developers building in Mumbra

Other RERA-registered projects in Thane

Sudama Vallabh Wing A,b,c
declared completion Jun 2026 · Pravin Vandravandas Vora
Sudarshan CO-OP. Hsg. Soc. LTD
declared completion May 2026 · Gayatri Foundation
Sudarshan Garden Phase II
possession by Dec 2026 · Sudarshan Nirman Co
Sudarshan Vihar
possession by Dec 2029 · Not Available
Sugar Loaf Studios
declared completion Jul 2019 · Warren Gerald Connor
Sugee Lake District- Lake Trade Centre I
possession by Dec 2033 · Sugee Enterprises Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.