MahaRERA Property Intelligence · Raigarh

SUKHKARTA 1

P52000010590 · promoter Image Builders

Certificate SignedDue 31 Dec 2018

Delivery & Registration

MahaRERA registrationP52000010590
Registered on31 Aug 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 91 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Image Builders is the promoter of record on 22 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
SUKHKARTA 11G+4-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Panvel, Raigarh, 410203. Per the filed land record, the plot is bounded to the north by SURVEY NO 57 4, to the south by INTERNAL ROAD, to the east by PLOT NO 2 and to the west by CTS NO 1662. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~51 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort50 km
Bandra Kurla Complex (BKC)51 km
Powai / Hiranandani business park51 km
Lower Parel / Worli business district51 km
Chhatrapati Shivaji Int'l Airport53 km
Andheri MIDC / SEEPZ55 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Image Builders is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Image Builders

Image Builders
Deregistered by MahaRERARaigarh

Other RERA-registered projects in Khopoli

Daata Eklavya Building A & B
possession by Aug 2026 · Daata Builders And Developers Private Li
Krishna Valley - Phase 3
possession by Aug 2026 · Prishti Venture Private Limited
Sanskruti
possession by Sep 2026 · Sandip Shankar Patil
Amansara Earthstar
possession by Nov 2026 · SVB Lifespaces LLP
Amansara Earthstar PH
possession by Nov 2026 · SVB Lifespaces LLP
Riddhi Siddhi Complex
Not filing quarterly progress reports · possession by Dec 2026 · Riddhi Siddhi Developers

Major developers building in Khopoli

Other RERA-registered projects in Raigarh

Sukhkarta 2
declared completion Dec 2018 · Image Builders
Suki-Nihon-Phase 2
possession by Jun 2027 · Nimesh Kirti Chhatbar
Sukoon
possession by Dec 2028 · Greensspaces
Sukoon Empire Bldg A AND B
possession by Apr 2030 · Sukoon Homes Builders AND Developers
Sukoon Residency
possession by Jun 2027 · Rifaa Structural Solutions Private Limit
Suman Apartment
declared completion Aug 2022 · Sadguru Mauli Developers

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.