MahaRERA Property Intelligence · Thane

SUMANGAL ANANT

P51700029262 · VILLAGE NAVAGAON NEAR ARUNODAY SOCIETY NAGAR DOMBIVLI WEST · promoter Sumangal Vastu Constructions

Certificate SignedDue 31 Dec 2023

Delivery & Registration

MahaRERA registrationP51700029262
Registered on10 May 2021
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sumangal Vastu Constructions is the promoter of record on 7 projects, of which 4 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
SUMANGAL ANANT1G+731 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at VILLAGE NAVAGAON NEAR ARUNODAY SOCIETY NAGAR DOMBIVLI WEST, MAHATMA PHULE ROAD, Kalyan, Thane, 421202. Per the filed land record, the plot is bounded to the north by NANDADEEP CO OP HSG SOCIETY, to the south by EXISTING SOCIETY ROAD AND ARUNODAY SOCIETY GROUND, to the east by CHINAR BUNGLOW and to the west by 15 MTR WIDE MAHATMA PHULE ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Palava

Evaan
possession by Jul 2026 · Impressions NXT
Saraswati Devi Krupa
possession by Jul 2026 · Yogiraj Heritage
JAI Malhar Plaza
possession by Aug 2026 · Swaminarayan Residency
Amar Elegance
possession by Sep 2026 · Amar Realty
Purva Prime
possession by Sep 2026 · Trimurti Constructions
Anant AND Radhika Heights
possession by Dec 2026 · Ashapura Construction CO

Major developers building in Palava

Other RERA-registered projects in Thane

Sumant CHS LTD
possession by Oct 2028 · GPS Lifespace
Sumati Skyline
possession by Sep 2026 · Subhash Skyline Infra
Sumeet Elite
possession by May 2027 · Vedant Construction
Sumeru Hills
possession by Dec 2029 · Tesco Realty LLP
Sumit Star Exclusif
possession by Jun 2027 · Sumit Star Land Developers LLP
Sumitra Heights
declared completion Mar 2026 · Swami Narayan Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026