MahaRERA Property Intelligence · Mumbai Suburban

Suvidha CHS Ltd

P51800004792 · promoter Ami Monika Developers

Certificate SignedDue 31 Mar 2018

Delivery & Registration

MahaRERA registrationP51800004792
Registered on09 Aug 2017
Promoter-declared completion31 Mar 2018
Current statusCertificate Signed
Against todayabout 100 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Ami Monika Developers is the promoter of record on 3 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
Suvidha CHS Ltd1G+10-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400077. Per the filed land record, the plot is bounded to the north by 27 mt wide proposed D P road, to the south by 9 15 mt wide existing road, to the east by Building of Sumit CHS Ltd and to the west by Building of Om Shreyas CHS Ltd. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Bandra Kurla Complex (BKC)4 km
Chhatrapati Shivaji Int'l Airport4 km
Powai / Hiranandani business park4 km
Andheri MIDC / SEEPZ7 km
Lower Parel / Worli business district12 km
Nariman Point / Fort19 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ghatkopar East

Baldevsingh Thakur SRA Coop HSG SOC LTD
possession by Jul 2026 · Krishna Narsingrao Pimple
Palatina
possession by Jul 2026 · Tanishq Builders
Vihar Heights
possession by Aug 2026 · Saptrishi Homes LLP
Poonam Celeste
possession by Aug 2026 · PL7 Realty Pvt. Ltd.
Hema Apartments CO-Operative Housing Society Limited
possession by Sep 2026 · Hema Appartments CO-Operative Housing So
Centrona ZEN-A
possession by Dec 2026 · Elevated Avenue Realty LLP

Major developers building in Ghatkopar East

Other RERA-registered projects in Mumbai Suburban

Suvidha Pearl
declared completion Oct 2022 · Kalakruti Realtors Private Limited
Suvidha Solitaire
possession by Dec 2028 · Premier Infotech Pvt Ltd
Suvidha Square
declared completion Dec 2021 · Suvidha Milind Business Ventures
Suyash
declared completion Apr 2025 · Dvasuyash Construction LLP
Suyash Eminence
possession by Dec 2027 · Dvasuyash Construction LLP
Suyog
declared completion Dec 2025 · Shree Krishna Homes PVT LTD

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026