Mumbai/Project record

MahaRERA · the public record

SWAMI LEELA

Thane · ATHARVA PROMOTERS AND BUILDERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000014103

Delivery and registration

When is the project declared for completion?

SWAMI LEELA is registered with MahaRERA as P52000014103 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000014103
Registered on07 Nov 2017
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SWAMI LEELA record 29 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 29 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Atharva Promoters is the promoter of record on 93 projects registered with MahaRERA, 13 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

93projects

registered with MahaRERA

13flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SWAMI LEELA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
SWAMI LEELA1G+331 Dec 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2020The project is delayed due to heavy rainfall in last year and slow real estate market conditions. Also since march, 2020, due to corona pendamic, project has been delayed due to sh
30 Dec 202030 Dec 2022.We request you to extend our complete Date for the project “SWAMI lEELA “ from the date of 31/12/2019 extend till to 30/12/2022
30 Dec 202230 Dec 2024required extension for the project due to corona and slow real estate market conditions.

Location, Land & Connectivity

Located at Kalyan, Thane, 410101. Per the filed land record, the plot is bounded to the north by OPEN SPACE, to the south by 90, to the east by 6 M WIDE INTERNAL ROAD and to the west by OPEN SPACE. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~46 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park46 km
Bandra Kurla Complex (BKC)49 km
Chhatrapati Shivaji Int'l Airport49 km
Andheri MIDC / SEEPZ50 km
Lower Parel / Worli business district53 km
Nariman Point / Fort55 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Atharva Promoters AND Builders is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Atharva Promoters AND Builders

Atharva Promoters AND Builders
FlaggedRaigarh

Other RERA-registered projects in Neral

Arsh Apartment
possession by Sep 2026 · Mateen Rafique Patel
Naaz Plaza
possession by Sep 2026 · Prestige Reality
Labdhi Gardens Phase 6
possession by Dec 2026 · Labdhi Lifestyle Limited
Labdhi Gardens Phase 7
possession by Dec 2026 · Labdhi Lifestyle Limited
Labdhi Gardens Phase 8
possession by Dec 2026 · Labdhi Lifestyle Limited
RAJ Baug Phase - III
possession by Dec 2026 · Nehaldhara Realtors

Major developers building in Neral

Other RERA-registered projects in Raigarh

Swami Pratima
possession by Dec 2027 · Atharva Promoters AND Builders
Swami Sadan
possession by Dec 2026 · Anil Baburao Achrekar
Swamini Heights
possession by Mar 2029 · Vivek Chandrakant Keni
Swapnashilpa
possession by Jul 2029 · S S Buildcon
Swara Pride
declared completion Dec 2025 · Milind Rangarav Shinde
Swaraj Complex
possession by Mar 2028 · AMI Realty Developers LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026