MahaRERA Property Intelligence · Raigarh

SWAMI MAHIMA

P52000050696 · DHAMOTE · promoter Shree Samarth Developers

Certificate SignedDue 31 Dec 2026

Delivery & Registration

MahaRERA registrationP52000050696
Registered on28 Apr 2023
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today5 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
SWAMI MAHIMA1G+5-

Complaints & Orders

3 complaints are on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC1240090527/11/2024Ramchandra Digambar Kamble vs Shree Samarth Developerspending / no order on file
CC1240094630/11/2024Santosh Balu Kale vs Shree Samarth Developerspending / no order on file
CC1250305030/08/2025Sandesh Manohar Patange vs Shree Samarth Developersorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202431 Dec 2026In our city , Various construction projects is going on. Supply is more than demand. People gets multiple choices to choose their apartment. Therefore we are not achieveing our goa

Location, Land & Connectivity

Located at DHAMOTE, DHAMOTE, Karjat, Raigarh, 410101. Per the filed land record, the plot is bounded to the north by DATTU VIRLE, to the south by ROAD, to the east by SUNIL HINGAL and to the west by RAHUL GAVHANKAR. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~5586 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Lower Parel / Worli business district5586 km
Andheri MIDC / SEEPZ5587 km
Nariman Point / Fort5587 km
Chhatrapati Shivaji Int'l Airport5587 km
Bandra Kurla Complex (BKC)5588 km
Powai / Hiranandani business park5591 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shree Samarth Developers is the promoter on 7 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Shree Samarth Developers project & its RERA track record →

Other flagged projects by Shree Samarth Developers

Shree Samarth Developers
FlaggedThane
Shree Samarth Developers
FlaggedThane
Shree Samarth Developers
FlaggedThane
Shree Samarth Developers
FlaggedRaigarh
Shree Samarth Developers
FlaggedThane

Other RERA-registered projects in Neral

SAI Krupa Valley- Phase 1
possession by Aug 2026 · SAI Krupa Developers
Noble Apartment
possession by Aug 2026 · Asra Reality
Madina Complex
possession by Aug 2026 · Al-Hamd Developers
Arsh Apartment
possession by Sep 2026 · Mateen Rafique Patel
Naaz Plaza
possession by Sep 2026 · Prestige Reality
Aliza Apartments
possession by Dec 2026 · M/S SKY Homes

Major developers building in Neral

Other RERA-registered projects in Raigarh

Swami Pratima
possession by Dec 2027 · Atharva Promoters AND Builders
Swami Residency
declared completion Jun 2025 · S P Group Builders AND Developers
Swami Sadan
possession by Dec 2026 · Anil Baburao Achrekar
Swami Sadan Apartment
possession by Sep 2027 · Rajesh Pradeep Lawate
Swami Samarth Residency
declared completion Aug 2023 · Sandeep Dnyandev Shankar Nanaware
Swami Sanidhya
declared completion Dec 2025 · Nitin Suryakant Mhatre

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.